Jefferson Power Station
A permitted 754 megawatt natural gas-fired combined-cycle plant at the White Bluff site, with the Arkansas Public Service Commission granting a certificate on January 28, 2026 and setting official benchmark costs that sum to $1,511,800,000.
Show on the map: Jefferson Power Station
- Certificate and official cost benchmarkThe Arkansas Public Service Commission's official Order No. 8 in Docket 25-047-U, issued January 28, 2026, grants Entergy Arkansas, LLC a certificate of convenience and necessity to construct Jefferson Power Station, a 754 megawatt natural gas-fired combined-cycle combustion turbine plant at the company's existing White Bluff site in Jefferson County. Ordering paragraph 10 finds that Entergy Arkansas presented evidence as to an estimated total investment amount of $1.512 billion, which includes $27.8 million for transmission interconnection project costs and $1.484 billion for generation project costs, and states that those two official amounts shall be used as the benchmark cost levels going forward. The map figure is the exact official component sum of $1,511,800,000, labeled $1.51 billion.Arkansas Public Service Commission, Jan 28, 2026
- Schedule and a higher company estimateThe official order records testimony confirming that the expected in-service date of the project is November 2029. The same official order also recounts company testimony that the plant would cost an estimated $1.602 billion, including approximately $1.574 billion for the generation portion and $27.8 million in estimated interconnection costs. That official record of the company's higher estimate is not used to replace the Commission's $1.512 billion estimated total and the official component benchmarks used on the map. This pass did not find a later official construction-start confirmation in Order No. 8. The map pin remains listed as permitted.Arkansas Public Service Commission, Jan 28, 2026
Next gate
Expected in-service date of November 2029
November 2029, according to official testimony recorded in the January 28, 2026 order
The official order records testimony confirming an expected in-service date of November 2029. This pass did not find a later official construction-start confirmation in that order. The map pin remains listed as permitted.
Every step so far, and what comes next
-
DoneJanuary 28, 2026
Commission grants a certificate and sets official benchmark costs summing to $1,511,800,000
Official Order No. 8 granted Entergy Arkansas a certificate to construct the 754 megawatt Jefferson Power Station and set official benchmark costs of $1.484 billion for generation and $27.8 million for transmission interconnection, the exact sum used on the map, with testimony confirming an expected in-service date of November 2029.
-
NextNovember 2029, according to official testimony recorded in the January 28, 2026 order
Expected in-service date
The official order records that expected in-service date. The map pin remains listed as permitted.
Worth knowing
- The map figure is the exact official component sum of $1,511,800,000, from the official $1.484 billion generation benchmark and $27.8 million transmission-interconnection benchmark in Ordering Paragraph 10. The same official paragraph states an estimated total investment amount of $1.512 billion. That official rounded total is recorded here and is not used to replace the exact component sum used on the map.
- Official Order No. 8 also recounts a company estimate of $1.602 billion. That higher official-record company figure is not used to replace the Commission's official benchmark.
- This pass did not find a later official construction-start confirmation in the January 28, 2026 order. The map pin remains listed as permitted, and this page does not change any map stage field.