Lightstone Jones Road data center
Spartanburg County enacted Ordinance O-26-35 on November 16, 2026, authorizing a development agreement for a data center of up to 65 IT megawatts at or near 430 Jones Road, with an anticipated investment of about $1.5 billion.
Show on the map: Lightstone Jones Road data center
- InvestmentOfficial Ordinance No. O-26-35, enacted November 16, 2026, recites that 300 Jones Road Associates LLC has represented that the project will involve an anticipated investment in the county of approximately One Billion, Five Hundred Million Dollars ($1,500,000,000), the figure used on the map, and the creation of at least 25 full-time jobs. The development agreement attached to the ordinance states that the company and its customers intend to make a total capital investment of $1.5 billion in the project, and that the required investment amount shall be at least $100 million.Spartanburg County, Nov 16, 2026
- Site and capacityThe official ordinance and agreement cover approximately 137 acres of real property at or near 430 Jones Road in Spartanburg County, identified as Tax Map Parcel No. 3-08-00-085.00 (137.220 acres). The agreement describes a data center with capacity up to 65 information technology (IT) megawatts, and lists permitted power capacity of up to 65 IT megawatts.Spartanburg County, Nov 16, 2026
- Community benefit paymentsThe official development agreement says that during the term the company shall contribute $9,000,000 in Community Benefit Payments to a community foundation or similar public charity as fiduciary, for uses such as workforce training, education partnerships, and road improvements. The agreement calls those payments voluntary charitable commitments, and says they do not constitute a tax, fee, impact fee, exaction, or condition of any permit. That $9 million is a community payment and is not used to replace the map's $1.5 billion investment figure.Spartanburg County, Nov 16, 2026
- Approval and scheduleCounty Council enacted the ordinance on November 16, 2026, after first reading on October 19, 2026, and second reading on November 3, 2026, with public hearings on November 3 and November 16, 2026. The official agreement has a five-year term from its effective date, extendable by mutual agreement. It says the company shall commence construction no later than the first anniversary of the last development approval, or after any legal challenges to those approvals have been resolved, and shall achieve substantial completion no later than the fifth anniversary of the last development approval, subject to extension for force majeure, including delays in state or federal permits.Spartanburg County, Nov 16, 2026
Next gate
Construction is to start by the first anniversary of the last development approval
After the official November 16, 2026 ordinance
The official agreement requires construction to start no later than the first anniversary of the last development approval, subject to force majeure and the resolution of any legal challenges. This pass did not find an official construction start. The map pin remains listed as announced.
Every step so far, and what comes next
-
DoneOctober 19, 2026
First reading of the Jones Road development agreement ordinance
The official ordinance records first reading on October 19, 2026.
Source: Spartanburg County, Nov 16, 2026
-
DoneNovember 3, 2026
Second reading and first public hearing
The official ordinance records second reading and the first public hearing on November 3, 2026.
Source: Spartanburg County, Nov 16, 2026
-
DoneNovember 16, 2026
County Council enacts Ordinance O-26-35
Spartanburg County Council enacted Ordinance O-26-35 on third reading after a second public hearing, authorizing the development agreement for a data center of up to 65 IT megawatts at or near 430 Jones Road, with an anticipated investment of about $1.5 billion.
Source: Spartanburg County, Nov 16, 2026
-
NextAfter the official November 16, 2026 ordinance
Construction is to start by the first anniversary of the last development approval
The official agreement requires construction to start no later than the first anniversary of the last development approval, subject to force majeure and the resolution of any legal challenges. This pass did not find an official construction start. The map pin remains listed as announced.
Source: Spartanburg County, Nov 16, 2026
Worth knowing
- The map figure is the official anticipated or intended $1.5 billion investment recited in Ordinance O-26-35 and the attached development agreement. The same official agreement states that the required investment amount shall be at least $100 million. The required minimum is not used to replace the map figure, and this page does not change any map usd field.
- The official $9 million Community Benefit Payments are voluntary charitable commitments and are not added to, or used to replace, the investment figure.
- The official ordinance and agreement name the company as 300 Jones Road Associates LLC, a Delaware limited liability company. The text extracted this pass does not identify Lightstone Group. This page does not change the map pin name.
- County Council enacted the ordinance and approved the development agreement on November 16, 2026. This pass did not find an official construction start. The map pin remains listed as announced, and this page does not change any map stage field.
Go deeper
Last checked Nov 24, 2026. We add a step when it happens and link the source.