Francis Scott Key Bridge rebuild
A new cable-stayed Key Bridge with a 1,665-foot main span, officially in a $4.3 billion to $5.2 billion range, with foundation work underway and a 2030 traffic-opening goal.
Show on the map: Francis Scott Key Bridge rebuild
- InvestmentOn November 20, 2025, MDTA updated the estimated cost range to $4.3 billion to $5.2 billion. The map counts the low end, $4.3 billionMaryland Department of Transportation, Nov 20, 2025
- DesignThe same 2025 update said the new bridge's main span is 1,665 feet, with taller towers and a pier-protection system, including protective fenders larger than a football field, and a 230-foot-high bridge deckMaryland Department of Transportation, Nov 20, 2025
- ScheduleThe November 2025 update gave an anticipated open-to-traffic date in late 2030. A November 19, 2026 MDTA release still described a goal of opening the new bridge to traffic by 2030, with the schedule to be refined as remaining contracts are awardedMaryland Department of Transportation, Nov 20, 2025
- Work underwayThe November 19, 2026 release said work is actively taking place, that crews are installing permanent foundation and pier-protection piles, and that temporary over-water work platforms, known as trestles, have been finished. The Board that day awarded a $38.6 million demolition and miscellaneous marine-work contract, with that demolition expected to begin later in the fallMaryland Transportation Authority, Nov 19, 2026
- Remaining contractsMDTA is advancing the remaining work in separate procurements: south land approach construction in spring 2027, north land approach in late spring 2027, and the main span and marine approaches in summer 2027Maryland Transportation Authority, Nov 19, 2026
Next gate
Award remaining approach and main-span contracts and continue foundation work
Land approaches in spring 2027; main span and marine approaches in summer 2027
The November 19, 2026 MDTA release said demolition and marine work under the newly awarded contract was expected to begin later in the fall, while three other procurements advance and foundation and pier-protection work continues.
Every step so far, and what comes next
-
DoneNovember 20, 2025
Cost range updated to $4.3 billion to $5.2 billion
MDTA updated the estimated cost and gave an anticipated open-to-traffic date in late 2030.
-
DoneNovember 19, 2026
Demolition contract awarded; foundation work underway
MDTA awarded a $38.6 million demolition and marine-work contract and said crews are installing permanent foundation and pier-protection piles, with trestles already finished.
-
NextSpring and summer 2027
Land approaches and main span construction
The planned start windows in the November 19, 2026 release for the remaining major construction contracts.
-
Expected2030
Open to traffic
The official goal, described as late 2030 in 2025 and as 2030 in the November 2026 release.
Worth knowing
- The map counts $4.3 billion, the low end of MDTA's official November 2025 range of $4.3 billion to $5.2 billion. The November 2026 contract-award release did not publish a new total.
- Foundation and pier-protection work is underway, but the land-approach and main-span construction contracts were not yet under construction in the November 19, 2026 release.
- The 2030 opening is an official goal and may move as remaining contracts are awarded.
Last checked Nov 23, 2026. We add a step when it happens and link the source.