Francis Scott Key Bridge rebuild

Maryland Transportation Authority · Over the Patapsco River, Baltimore, Maryland

Under construction, with major span contracts still ahead

A new cable-stayed Key Bridge with a 1,665-foot main span, officially in a $4.3 billion to $5.2 billion range, with foundation work underway and a 2030 traffic-opening goal.

Show on the map: Francis Scott Key Bridge rebuild

Next gate

Award remaining approach and main-span contracts and continue foundation work

Land approaches in spring 2027; main span and marine approaches in summer 2027

The November 19, 2026 MDTA release said demolition and marine work under the newly awarded contract was expected to begin later in the fall, while three other procurements advance and foundation and pier-protection work continues.

Every step so far, and what comes next

  1. DoneNovember 20, 2025

    Cost range updated to $4.3 billion to $5.2 billion

    MDTA updated the estimated cost and gave an anticipated open-to-traffic date in late 2030.

  2. DoneNovember 19, 2026

    Demolition contract awarded; foundation work underway

    MDTA awarded a $38.6 million demolition and marine-work contract and said crews are installing permanent foundation and pier-protection piles, with trestles already finished.

  3. NextSpring and summer 2027

    Land approaches and main span construction

    The planned start windows in the November 19, 2026 release for the remaining major construction contracts.

  4. Expected2030

    Open to traffic

    The official goal, described as late 2030 in 2025 and as 2030 in the November 2026 release.

Worth knowing

Last checked Nov 23, 2026. We add a step when it happens and link the source.