Korea Zinc Project Crucible smelter, Clarksville
An integrated critical minerals smelter designed to make 13 nonferrous metals, 11 of them on the U.S. critical minerals list.
Show on the map: Korea Zinc Crucible smelter
- Capital spending$6.6 billion; Korea Zinc puts total planned investment at $7.4 billion including working capital and financing costsTennessee Department of Economic and Community Development, Dec 15, 2025
- SiteAbout 650,000 square meters at the Nyrstar siteTennessee Department of Economic and Community Development, Dec 15, 2025
- OperationsPhased commercial operations targeted from 2029Tennessee Department of Economic and Community Development, Dec 15, 2025
Next gate
Full-scale construction starts
2027 (company plan)
Korea Zinc says full-scale construction starts in 2027.
Every step so far, and what comes next
-
DoneDec 15, 2025
Korea Zinc announces the project with the U.S. government
Korea Zinc announced Project Crucible with the U.S. Departments of War and Commerce. Tennessee called it the largest private investment in state history.
Source: Tennessee Department of Economic and Community Development, Dec 15, 2025
-
Next2027 (company plan)company target
Full-scale construction starts
Korea Zinc says full-scale construction starts in 2027.
Source: Tennessee Department of Economic and Community Development, Dec 15, 2025
-
ExpectedFrom 2029 (company target)company target
First phased operations
Phased commercial operations are targeted from 2029.
Source: Tennessee Department of Economic and Community Development, Dec 15, 2025
Worth knowing
- The federal support is an initial, conditional commitment, per Korea Zinc.
- Tennessee's $6.6 billion figure also covers reopening a former mine in Gordonsville, Smith County; Korea Zinc attaches the $6.6 billion to the Clarksville smelter.
Last checked Nov 28, 2026. We add a step when it happens and link the source.