Kosciusko Junction Pipeline Project (Gulf South and Texas Gas)

Boardwalk Pipelines (Gulf South Pipeline and Texas Gas Transmission) · Kosciusko Compressor Station area, Attala County, Mississippi, with facilities also in Washington, Sunflower, Humphreys, Holmes, Leake, Newton, Jasper, and Clarke counties

Permitted

Official FERC order 196 FERC 61,190, issued September 10, 2026, authorized Gulf South and Texas Gas to construct the Kosciusko Junction Pipeline Project, with company cost estimates of $1,031,400,000 and $79.5 million.

Show on the map: Kosciusko Junction Pipeline Project (Gulf South and Texas Gas)

Next gate

Official September 10, 2026 FERC order issued certificates for the project

After the official September 10, 2026 certificate order

The official FERC order authorized the Kosciusko Junction Pipeline Project, subject to conditions, and recorded company cost estimates of $1,031,400,000 for Gulf South and $79.5 million for Texas Gas. This pass did not open a later official notice to proceed. The map pin remains listed as permitted.

Every step so far, and what comes next

  1. DoneSeptember 12, 2025

    Gulf South and Texas Gas file a joint certificate application

    The official September 10, 2026 order says the companies filed a joint application on September 12, 2025, requesting authorization to construct and operate the Kosciusko Junction Pipeline Project.

  2. DoneSeptember 10, 2026

    FERC issues certificates and approves abandonments

    Official order 196 FERC 61,190 authorized the project, subject to conditions, and recorded official cost estimates of $1,031,400,000 for Gulf South and $79.5 million for Texas Gas.

  3. NextAfter the official September 10, 2026 certificate order

    Official September 10, 2026 FERC order issued certificates for the project

    The official FERC order authorized the Kosciusko Junction Pipeline Project, subject to conditions, and recorded company cost estimates of $1,031,400,000 for Gulf South and $79.5 million for Texas Gas. This pass did not open a later official notice to proceed. The map pin remains listed as permitted.