Lariat Wind Project
A permitted 800 megawatt wind project in Bailey and Parmer counties, authorized by the Public Utility Commission of Texas on October 15, 2026, with an official estimated cost of $2,284,313,400 including AFUDC and a commercial operation date of February 2029.
Show on the map: Lariat Wind Project
- Certificate and official costThe Public Utility Commission of Texas's October 15, 2026 official order in Docket 58664 amends Southwestern Public Service Company's certificate to authorize construction of the Lariat wind project. Finding of fact 29 states that the project would be located in Bailey and Parmer counties, Texas, interconnect to SPS's existing Tolk generating station, have a nameplate capacity of 800 megawatts, and have a commercial operation date of February 2029, with a total estimated cost of approximately $1.999 billion excluding AFUDC and $2,284,313,400 including AFUDC, the figure used on the map. Finding of fact 35 states that those official totals include all facilities necessary to serve customers from the project. The Commission approved the Lariat and Yellow House wind projects with a minimum production guarantee, rather than a capital-cost cap of the kind set for the Gaines County and Tolk Station combustion-turbine projects in the same order.Public Utility Commission of Texas, Oct 15, 2026
- Scope and a separate sister plantThe same official order authorizes several other separately identified self-build generation projects, including the Yellow House wind project. Only the official Lariat cost is included here. This pass did not find a later official confirmation in that order that construction had begun. The map pin remains listed as permitted.Public Utility Commission of Texas, Oct 15, 2026
Next gate
Commercial operation targeted
February 2029, according to official finding of fact 29
The official October 15, 2026 order states a commercial operation date of February 2029. This pass did not find a later official construction-start confirmation in that order. The map pin remains listed as permitted.
Every step so far, and what comes next
-
DoneOctober 15, 2026
Commission authorizes the 800 megawatt Lariat wind project
The official PUCT order amended SPS's certificate to authorize the Lariat wind project in Bailey and Parmer counties and stated an official estimated cost of $2,284,313,400 including AFUDC, the figure used on the map, with a commercial operation date of February 2029.
-
NextFebruary 2029, according to official finding of fact 29
Commercial operation targeted
The official order states a commercial operation date of February 2029. The map pin remains listed as permitted.
Worth knowing
- The map figure is the official estimated cost of $2,284,313,400 including AFUDC in finding of fact 29, labeled $2.28 billion. The same official finding also states a total estimated cost of approximately $1.999 billion excluding AFUDC. That official estimate is recorded here and is not used to replace the AFUDC-inclusive figure used on the map.
- Unlike the Gaines County and Tolk Station CT projects in the same official order, the Commission approved this wind project with a minimum production guarantee rather than a capital-cost cap.
- Other generation projects authorized in the same official docket, including the Yellow House wind project, are separate and are not added to this pin. This pass did not find a later official construction-start confirmation in the order. The map pin remains listed as permitted, and this page does not change any map stage field.