I-635 LBJ East Project, Dallas

Texas Department of Transportation · I-635 from just east of US 75 in North Dallas to I-30 in Mesquite, Dallas County, Texas

Under construction

An 11 mile rebuild of I-635 in Dallas County, 97 percent complete in TxDOT's official October 2026 district list at an estimated cost of $1.7 billion, with finish scheduled for late 2026.

Show on the map: I-635 LBJ East Project, Dallas

Next gate

Finish scheduled for late 2026

Late 2026, according to the official October 2026 Dallas District construction list, which reported the work as 97 percent complete

The official October 2026 district list scheduled finish for late 2026 and reported the project as 97 percent complete. This pass, on November 24, 2026, did not find a later official completion notice. The map pin remains listed as under construction.

Every step so far, and what comes next

  1. DoneSpring 2020

    Construction began

    The official 635 East Project page says construction began in the spring of 2020.

  2. DoneOctober 2026

    Official district list reports $1.7 billion and 97 percent complete

    TxDOT's official Dallas County construction list for October 2026 stated an estimated cost of $1.7 billion, the figure used on the map, and reported the project as 97 percent complete, with finish scheduled for late 2026.

  3. NextLate 2026, according to the official October 2026 list

    Finish scheduled

    The official October 2026 list scheduled finish for late 2026. This pass did not find a later official completion notice. The map pin remains listed as under construction.

Worth knowing

Go deeper

Last checked Nov 24, 2026. We add a step when it happens and link the source.