LG Energy Solution battery complex, Queen Creek
A $5.5 billion stand-alone complex for cylindrical EV batteries and LFP energy-storage batteries, now under construction.
Show on the map: LG Energy Solution battery complex
- Investment$5.5 billion (about KRW 7.2 trillion), the figure used on the map, from LG Energy Solution's March 24, 2023 announcementLG Energy Solution, Mar 24, 2023
- Original scopeThe 2023 announcement described two plants: a $3.2 billion cylindrical EV battery plant of 27 GWh, then aimed at 2170 cells with mass production in 2025, and a $2.3 billion LFP pouch ESS plant of 16 GWh, with production aimed at 2026, for a combined 43 GWhLG Energy Solution, Mar 24, 2023
- Updated scopeA April 3, 2024 Town of Queen Creek release, quoting LG Energy Solution Arizona President Richard Ra, said the cylindrical plant would make 46-Series EV batteries and that full-complex capacity was expected to reach 53 GWh (36 GWh cylindrical and 17 GWh LFP ESS)Town of Queen Creek, Apr 3, 2024
- JobsThe April 5, 2025 company update said the project would create 1,500 new employment opportunities by 2027LG Energy Solution, Apr 5, 2025
- ProgressThe April 5, 2025 company update said the cylindrical plant was about halfway complete, with sample production aimed at mid-2026 and commercial production by the end of 2026LG Energy Solution, Apr 5, 2025
Next gate
Start of U.S. 46-Series cylindrical battery production
By the end of 2026
LG Energy Solution's November 3, 2026 earnings release said the company plans to begin U.S. production of 46-Series cylindrical batteries by the end of 2026. That matches the April 2025 Queen Creek update, which aimed at commercial production of those cells by year-end 2026.
Every step so far, and what comes next
-
DoneMarch 24, 2023
Queen Creek complex announced
LG Energy Solution announced a $5.5 billion stand-alone battery complex, then planned at 43 GWh, with groundbreaking in 2023.
Source: LG Energy Solution, Mar 24, 2023
-
DoneNovember 2023
Groundbreaking
The April 3, 2024 Town of Queen Creek release said President Ra reported the project had been underway since a groundbreaking the previous November, with steel beams then being placed.
Source: Town of Queen Creek, Apr 3, 2024
-
DoneApril 5, 2025
Cylindrical plant about halfway complete
LG Energy Solution said the cylindrical plant was about halfway done, with sample production aimed at mid-2026 and commercial production by the end of 2026, and 1,500 jobs by 2027.
Source: LG Energy Solution, Apr 5, 2025
-
NextBy the end of 2026
Start of U.S. 46-Series cylindrical battery production
The date given in the November 3, 2026 earnings release.
Source: LG Energy Solution, Nov 3, 2026
Worth knowing
- The map pin is still marked announced. Official local and company updates since 2024 describe construction well underway. This tracker treats the complex as under construction. The map usd figure was left unchanged.
- Official capacity and cell-type figures changed after the 2023 announcement, from 43 GWh (27 GWh of 2170 cells plus 16 GWh of ESS) to 53 GWh (36 GWh of 46-Series cells plus 17 GWh of ESS) in the 2024 town update.
- The November 2026 earnings release says a new Arizona link production line for ESS is complete and that U.S. 46-Series cylindrical production is planned by the end of 2026. It does not say the full Queen Creek complex has entered mass production.
- The 1,500-job figure is from the April 2025 company update. Earlier local remarks referred more generally to thousands of jobs.
Last checked Nov 23, 2026. We add a step when it happens and link the source.