Livingston County CCGT
A proposed approximately 1,400 megawatt combined-cycle plant with $3.9 billion of estimated capital costs in DTE Electric's 2026 integrated resource plan, with official service targeted by year-end 2031.
Show on the map: Livingston County CCGT
- Investment and capacityDTE Electric's official 2026 Integrated Resource Plan executive summary, filed September 24, 2026, lists a Certificate of Necessity request for the Livingston County CCGT project of approximately 1,400 megawatts and $3.9 billion of estimated capital costs, the figure used on the map. A same-day company news release said DTE Electric was proposing two new natural gas plants totaling 2.1 gigawatts as part of the plan filed with the Michigan Public Service Commission.DTE Electric, Sep 24, 2026
- ScheduleThe official executive summary's near-term milestone table says the Livingston County CCGT, approximately 1,400 megawatts, enters service by year-end 2031. It lists continued development of the Livingston County and Monroe County CCGT projects in 2028 and continued CCGT development in 2029. This pass did not find a more specific official construction-start month in the executive summary.DTE Electric, Sep 24, 2026
- Role in the planThe official executive summary presents the plant as part of 2.2 gigawatts of high-efficiency natural gas in the proposed course of action and says these facilities will be designed to accommodate carbon capture and storage technology. The same document's longer-term timeline lists carbon capture and storage at two CCGT facilities entering service in 2035. The two-plant CCS date is a later plan milestone, not a replacement for the 2031 in-service target.DTE Electric, Sep 24, 2026
Next gate
Plant targeted to enter service
By year-end 2031, according to the official 2026 IRP executive summary
The official executive summary says the approximately 1,400 megawatt Livingston County CCGT enters service by year-end 2031. DTE Electric is seeking a Certificate of Necessity from the Michigan Public Service Commission. This pass did not find a later official construction-start announcement.
Every step so far, and what comes next
-
DoneSeptember 24, 2026
DTE Electric filed its 2026 IRP including the plant
DTE Electric filed its 2026 integrated resource plan with the Michigan Public Service Commission, listing a Certificate of Necessity request for an approximately 1,400 megawatt Livingston County CCGT with $3.9 billion of estimated capital costs.
Source: DTE Electric, Sep 24, 2026
-
NextBy year-end 2031
Plant targeted to enter service
The official IRP executive summary says the Livingston County CCGT enters service by year-end 2031.
Source: DTE Electric, Sep 24, 2026
Worth knowing
- The $3.9 billion figure is an estimated capital cost in DTE Electric's 2026 IRP, not an approved construction budget.
- The official executive summary names the plant as a Livingston County project and does not, in the materials reviewed here, give a township-level site.
- The $3.5 billion plan-wide savings figure in the September 24, 2026 company release compares the full IRP with a prior filing and is not a replacement for this plant's $3.9 billion estimated capital cost.
- The tracker stage is announced, matching the map. This page does not change any map usd, stage, or pledge field.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.