Long Bridge Project, Arlington to Washington
A 1.8 mile rail corridor adding a new two-track Potomac River bridge and related structures, with official North and South package budgets totaling $2.6647 billion and completion estimated in 2030.
Show on the map: Long Bridge Project, Arlington to Washington
- InvestmentVPRA's November 2026 Executive Director's Report lists a Long Bridge North package project cost of $1,648.4 million and a Long Bridge South package project cost of $1,016.3 million. Those official package budgets sum to $2,664.7 million, the figure used on the map and rounded there to $2.66 billion. Both packages have an estimated completion year of 2030 and are listed as final design and constructionVirginia Passenger Rail Authority, Nov 2026
- ScopeVPRA's official Long Bridge project page, reviewed on November 23, 2026, describes a 1.8 mile rail improvement that will create a continuous four-track corridor between the Long Bridge Aquatic Center in Arlington and L'Enfant Plaza in Washington, D.C. It includes five new rail bridges and two new pedestrian and bicycle bridges, including a new two-track rail bridge over the Potomac River next to the existing Long Bridge and a new bike and pedestrian bridge connecting Long Bridge Park and the Mount Vernon Trail in Arlington to East Potomac Park in D.C.Virginia Passenger Rail Authority, Nov 23, 2026
- Construction progressThe November 2026 report says the North package contractor is the Skanska-Flatiron-Dragados joint venture, with Retaining Wall L foundations nearing completion, Maine Avenue rail bridge foundations continuing, pile driving for Retaining Wall G, foundation construction started at the I-395 rail bridge, and the Washington Channel trestle complete. The South package contractor is Long Bridge Rail Partners. The report says pile driving in the Potomac River began in early November, and that the largest concrete placement on the project, 575 cubic yards at the northern abutment, was completed on October 10Virginia Passenger Rail Authority, Nov 2026
Next gate
Near-term Long Bridge milestones, then a 2030 completion
Retaining Wall L targeted no later than January 31, 2027; packages estimated to complete in 2030
The November 2026 official report targets substantial completion of Retaining Wall L on the North package no later than January 31, 2027, and substantial completion of Abutment B on the north shore of the Potomac no later than August 1, 2027. Both packages have an estimated completion year of 2030.
Every step so far, and what comes next
-
DoneOctober 10, 2026
Largest concrete placement completed at the northern abutment
The November 2026 VPRA report said Long Bridge Rail Partners completed the project's largest concrete placement, 575 cubic yards, on October 10.
-
DoneEarly November 2026
Pile driving in the Potomac River began
The same official report said pile driving in the Potomac River began in early November.
-
NextNo later than January 31, 2027
Substantial completion of Retaining Wall L targeted
The November 2026 report lists substantial completion of Retaining Wall L on the North package no later than January 31, 2027, with both packages still estimated to complete in 2030.
Worth knowing
- The map figure is the sum of the two official package budgets in the November 2026 report, $1,648.4 million and $1,016.3 million, not a separately published single-line program total.
- The corridor also includes work in the District of Columbia. The map pin is in Arlington.
- This page does not add later or earlier cost figures from older project documents on top of the November 2026 package budgets.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.
Tracking saves to this device only. No account, no email, free.