Longshore-Drill Hole 765 kV Transmission Line
A permitted 181.6 mile, 765-kilovolt transmission line between Howard and Culberson counties, with an official total estimated cost of $1,703,882,000 after a Public Utility Commission of Texas order on August 28, 2026.
Show on the map: Longshore-Drill Hole 765 kV Transmission Line
- InvestmentThe Public Utility Commission of Texas's August 28, 2026 official order in Docket 59029 amends Oncor's certificate of convenience and necessity to include the Longshore switch-to-Drill Hole switch 765-kilovolt transmission facilities along route 476. Finding of fact 132 states that the total estimated cost to construct those facilities along route 476 is approximately $1,703,882,000, the figure rounded to $1.70 billion on the map. Findings 130 and 131 break that official total into an estimated construction cost for route 476 of $975,821,000, excluding station costs, and $728,061,000 of station work, including new 765-kilovolt switchyards at both Longshore switch and Drill Hole switch.Public Utility Commission of Texas, Aug 28, 2026
- Scope and scheduleThe same official order states that route 476 is approximately 181.6 miles in length, from Oncor's Longshore switch about 4.5 miles west of Forsan in Howard County to Oncor's Drill Hole switch in Culberson County. The line also crosses Andrews, Ector, Glasscock, Loving, Martin, Midland, Reeves, and Winkler counties. In the application, Oncor estimated it would acquire all right-of-way by June 2027, complete construction by December 2028, and energize the facilities by December 2028, estimates premised on Commission approval within 180 days of filing.Public Utility Commission of Texas, Aug 28, 2026
Next gate
Right-of-way, construction, and energization on the application schedule
Right-of-way estimated by June 2027 and energization by December 2028, according to the official August 28, 2026 order
The official order records Oncor's estimate that it would acquire all right-of-way by June 2027 and energize the facilities by December 2028, premised on Commission approval within 180 days of filing. The project remains permitted. This pass did not find a later official construction-start confirmation.
Every step so far, and what comes next
-
DoneAugust 28, 2026
Commission approves route 476 and a $1,703,882,000 official cost
The Public Utility Commission of Texas amended Oncor's certificate to include the Longshore-to-Drill Hole 765-kilovolt facilities along route 476 and found a total estimated cost of approximately $1,703,882,000, the figure used on the map.
-
NextDecember 2028, according to the estimate recorded in the official order
Energization targeted, if the application schedule holds
Oncor estimated it would complete construction and energize the facilities by December 2028, premised on timely Commission approval. The map pin remains listed as permitted.
Worth knowing
- The map figure is the official total estimated cost of approximately $1,703,882,000 along approved route 476, labeled $1.70 billion. That official total includes $728,061,000 of station work at both Longshore switch and Drill Hole switch.
- The sister Dinosaur-Longshore 765-kilovolt project, approved the same day in Docket 59315, also includes official station work at Longshore switch in its own total. The two official certificate totals should not be added together as if the shared Longshore switchyard were unique to each project.
- Oncor's December 2028 energization estimate was premised on Commission approval within 180 days of filing. The map pin remains listed as permitted, and this page does not change any map stage field.