Longshore-Drill Hole 765 kV Transmission Line

Oncor Electric Delivery · From Oncor's Longshore switch west of Forsan in Howard County to Oncor's Drill Hole switch in Culberson County, Texas

Permitted

A permitted 181.6 mile, 765-kilovolt transmission line between Howard and Culberson counties, with an official total estimated cost of $1,703,882,000 after a Public Utility Commission of Texas order on August 28, 2026.

Show on the map: Longshore-Drill Hole 765 kV Transmission Line

Next gate

Right-of-way, construction, and energization on the application schedule

Right-of-way estimated by June 2027 and energization by December 2028, according to the official August 28, 2026 order

The official order records Oncor's estimate that it would acquire all right-of-way by June 2027 and energize the facilities by December 2028, premised on Commission approval within 180 days of filing. The project remains permitted. This pass did not find a later official construction-start confirmation.

Every step so far, and what comes next

  1. DoneAugust 28, 2026

    Commission approves route 476 and a $1,703,882,000 official cost

    The Public Utility Commission of Texas amended Oncor's certificate to include the Longshore-to-Drill Hole 765-kilovolt facilities along route 476 and found a total estimated cost of approximately $1,703,882,000, the figure used on the map.

  2. NextDecember 2028, according to the estimate recorded in the official order

    Energization targeted, if the application schedule holds

    Oncor estimated it would complete construction and energize the facilities by December 2028, premised on timely Commission approval. The map pin remains listed as permitted.

Worth knowing

Go deeper

Last checked Nov 24, 2026. We add a step when it happens and link the source.