Track your favorite projects · LNG export

Louisiana LNG

Woodside Energy · Near Lake Charles, Calcasieu Parish, Louisiana

Under construction, about a third done

Woodside's three-train LNG export plant on the Calcasieu River, the former Driftwood LNG.

Show on the map: Louisiana LNG

Next gate

First LNG

2029

Woodside says the project is on budget and targeting first LNG in 2029.

Every step so far, and what comes next

  1. Done2024

    Woodside buys the project

    Woodside acquired Driftwood LNG when it bought Tellurian.

  2. DoneApr 28, 2025

    Final investment decision

    Woodside approved $17.5 billion for the three-train foundation phase.

  3. DoneSep 30, 2026

    32% complete

    Train 1 at 41%, Train 2 at 27% and Train 3 at 22%; LNG Tank 1 wall concrete reached 50%.

  4. Next2029

    First LNG

    The company's target.

Worth knowing

Last checked Nov 23, 2026. We add a step when it happens and link the source.