Track your favorite projects · Transmission
LS Power Power the Bay transmission
A $2 billion Bay Area transmission program with official construction underway on two of three projects since March 30, 2026, and an official in-service target of June 1, 2028 for those two lines.
Show on the map: LS Power Power the Bay transmission
- Investment and scopeLS Power Grid California said on May 20, 2026, that it is investing $2 billion, the figure used on the map, in three Bay Area transmission projects known as Power the Bay. The official project site lists those projects as Power Santa Clara Valley, Power the South Bay, and Power the Valley Connector. The May 20 release said the Power the Bay projects will be capable of transmitting 1,000 megawatts, described as the equivalent of serving approximately 750,000 homes, and will create around 300 union jobs during construction.LS Power, May 20, 2026
- The two lines now in constructionThe official May 20, 2026 release said Power Santa Clara Valley will use HVDC technology to connect two new terminals, Skyline and Grove, in San Jose via a new 12-mile underground line, and that Power the South Bay will add a new 12-mile, 230 kV line, partly overhead and partly underground, linking the existing power system in Fremont and Santa Clara. A September 2026 LS Power Grid California update filed with the California Public Utilities Commission said both projects received CPCN decisions on March 19, 2026, started construction on March 30, 2026, and have a current projected in-service date of June 1, 2028.LS Power Grid California, filed with the California Public Utilities Commission, Sep 10, 2026
- Schedule and the third projectThe official Power the Bay site, retrieved November 23, 2026, said construction on Power the South Bay and Power Santa Clara Valley began in spring 2026, is anticipated to last approximately two years, and is planned to conclude with energization in 2028. It said construction of the Power the Valley Connector is targeted for 2028, after necessary permits, agreements, and land rights are received, with energization anticipated in 2030. The May 20, 2026 company release said the California ISO selected LS Power Grid California in 2023 to finance, construct, own, operate, and maintain the Power the Bay projects, and that in 2026 the ISO selected the company for the Power the Valley Connector.LS Power Grid California, Power the Bay, Nov 23, 2026
Next gate
Power Santa Clara Valley and Power the South Bay targeted to enter service
June 1, 2028, according to the September 2026 CPUC filing
The September 2026 LS Power Grid California update filed with the CPUC lists a current projected in-service date of June 1, 2028 for both Power Santa Clara Valley and Power the South Bay, unchanged from the original planned date. The official project site targets Valley Connector energization in 2030.
Every step so far, and what comes next
-
Done2023
California ISO selected LS Power Grid California
The official May 20, 2026 release said that in 2023 the California ISO selected LS Power Grid California to finance, construct, own, operate, and maintain the Power the Bay projects.
Source: LS Power, May 20, 2026
-
DoneMarch 19, 2026
CPUC issued CPCN decisions
The September 2026 CPUC-filed update lists March 19, 2026, as the date of CPUC certification of the final EIRs and CPCN decisions for Power Santa Clara Valley and Power the South Bay.
Source: LS Power Grid California, filed with the California Public Utilities Commission, Sep 10, 2026
-
DoneMarch 30, 2026
Construction started on the two lines
The same official update lists construction start on March 30, 2026, for both Power Santa Clara Valley and Power the South Bay.
Source: LS Power Grid California, filed with the California Public Utilities Commission, Sep 10, 2026
-
DoneMay 20, 2026
Ceremonial groundbreaking in San Jose and Fremont
LS Power Grid California held groundbreaking ceremonies in San Jose and Fremont and said it is investing $2 billion in three Bay Area transmission projects.
Source: LS Power, May 20, 2026
-
NextJune 1, 2028
Power Santa Clara Valley and Power the South Bay targeted to enter service
The September 2026 CPUC-filed update lists a current projected in-service date of June 1, 2028 for both projects. The official project site targets Valley Connector energization in 2030.
Source: LS Power Grid California, filed with the California Public Utilities Commission, Sep 10, 2026
Worth knowing
- The pin is at San Jose and covers three projects in Alameda and Santa Clara counties.
- The May 20, 2026 ceremonies marked a formal groundbreaking after construction had already started on March 30, 2026, according to the later CPUC-filed update.
- The May 20 release also cited more than $2.5 billion in California ISO competitive transmission awards to LS Power Grid California since 2020. That is a broader awards total, not a replacement for the $2 billion Power the Bay figure used on the map.
- The tracker stage is under construction, matching the map. This page does not change any map usd, stage, or pledge field.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.