Track your favorite projects · Transmission

LS Power Power the Bay transmission

LS Power Grid California · San Jose, Fremont, and Santa Clara, California (map pin at San Jose)

Under construction

A $2 billion Bay Area transmission program with official construction underway on two of three projects since March 30, 2026, and an official in-service target of June 1, 2028 for those two lines.

Show on the map: LS Power Power the Bay transmission

Next gate

Power Santa Clara Valley and Power the South Bay targeted to enter service

June 1, 2028, according to the September 2026 CPUC filing

The September 2026 LS Power Grid California update filed with the CPUC lists a current projected in-service date of June 1, 2028 for both Power Santa Clara Valley and Power the South Bay, unchanged from the original planned date. The official project site targets Valley Connector energization in 2030.

Every step so far, and what comes next

  1. Done2023

    California ISO selected LS Power Grid California

    The official May 20, 2026 release said that in 2023 the California ISO selected LS Power Grid California to finance, construct, own, operate, and maintain the Power the Bay projects.

  2. DoneMarch 19, 2026

    CPUC issued CPCN decisions

    The September 2026 CPUC-filed update lists March 19, 2026, as the date of CPUC certification of the final EIRs and CPCN decisions for Power Santa Clara Valley and Power the South Bay.

  3. DoneMarch 30, 2026

    Construction started on the two lines

    The same official update lists construction start on March 30, 2026, for both Power Santa Clara Valley and Power the South Bay.

  4. DoneMay 20, 2026

    Ceremonial groundbreaking in San Jose and Fremont

    LS Power Grid California held groundbreaking ceremonies in San Jose and Fremont and said it is investing $2 billion in three Bay Area transmission projects.

  5. NextJune 1, 2028

    Power Santa Clara Valley and Power the South Bay targeted to enter service

    The September 2026 CPUC-filed update lists a current projected in-service date of June 1, 2028 for both projects. The official project site targets Valley Connector energization in 2030.

Worth knowing

Go deeper

Last checked Nov 23, 2026. We add a step when it happens and link the source.