Marshall CTs
Duke Energy's official January 30, 2026 testimony in South Carolina Docket 2026-30-E describes an 850 megawatt simple-cycle facility under construction at Marshall Steam Station, with a Class 3 cost estimate of $1,440,377,238 including financing costs.
Show on the map: Marshall CTs
- Official cost and statusThe official January 30, 2026 direct testimony of John Robert Smith, Jr., filed with the Public Service Commission of South Carolina in Docket No. 2026-30-E, states that Duke Energy Carolinas is seeking a certificate for the 850 megawatt (425 megawatts each) simple-cycle combustion turbine facility under construction at DEC's Marshall Steam Station in Catawba County. The testimony says DEC's current Class 3 estimate for the Marshall CTs, including financing costs (AFUDC/CWIP), is $1,440,377,238, the figure used on the map, and that the companies expect to complete construction of the Marshall CTs in the fourth quarter of 2028. It also states that the North Carolina Utilities Commission has authorized construction and operation of the facilities.Duke Energy (filed with the Public Service Commission of South Carolina), Jan 30, 2026
- Estimate range not used to replace the official totalThe same official testimony says the Marshall CTs estimate has progressed to an AACE Class 3 estimate with an assessed predictability range of -10 percent ($1,296,339,514) to +25 percent ($1,800,471,548). Those official range figures are not used to replace the $1,440,377,238 Class 3 point estimate.Duke Energy (filed with the Public Service Commission of South Carolina), Jan 30, 2026
- Person County plants not addedThe same official testimony also discusses the Person County combined-cycle plants, which the testimony describes as separate facilities, with Person County CC1 expected in the fourth quarter of 2028 and CC2 in the fourth quarter of 2029. Those plants already have their own map pins and tracker pages, and their official costs are not added into this pin.Duke Energy (filed with the Public Service Commission of South Carolina), Jan 30, 2026
Next gate
Official testimony said the Marshall CTs were under construction, with completion expected in the fourth quarter of 2028
After the official January 30, 2026 testimony
The official testimony said the Marshall CTs were under construction at Marshall Steam Station and that the companies expect to complete construction in the fourth quarter of 2028. The map pin remains listed as under construction.
Every step so far, and what comes next
-
DoneJanuary 30, 2026
Duke Energy testimony describes the Marshall CTs as under construction at a Class 3 cost of $1,440,377,238
The official testimony filed in South Carolina Docket 2026-30-E states that the 850 megawatt simple-cycle Marshall CTs are under construction at Marshall Steam Station, that DEC's current Class 3 estimate including financing costs is $1,440,377,238, the figure used on the map, and that completion is expected in the fourth quarter of 2028.
Source: Duke Energy (filed with the Public Service Commission of South Carolina), Jan 30, 2026
-
NextAfter the official January 30, 2026 testimony
Official testimony said the Marshall CTs were under construction, with completion expected in the fourth quarter of 2028
The official testimony said the Marshall CTs were under construction at Marshall Steam Station and that the companies expect to complete construction in the fourth quarter of 2028. The map pin remains listed as under construction.
Source: Duke Energy (filed with the Public Service Commission of South Carolina), Jan 30, 2026
Worth knowing
- The map figure is the official Class 3 total project cost of $1,440,377,238 for the Marshall CTs, including financing costs (AFUDC/CWIP), as stated in Duke Energy's January 30, 2026 testimony. The official Class 3 predictability range of -10 percent to +25 percent is not used to replace that point estimate. This page does not change any map usd field.
- The Person County combined-cycle plants discussed in the same testimony are separate facilities and are not added into this pin.
- The official testimony states that the Marshall CTs are under construction. The map pin remains listed as under construction, and this page does not change any map stage field.
Go deeper
Last checked Nov 24, 2026. We add a step when it happens and link the source.