Meta El Paso data center
A 1 gigawatt AI data center campus under construction in El Paso, with capacity targeted to start coming online in 2028.
Show on the map: Meta El Paso data center
- Meta investmentMore than $10 billion, confirmed in March 2026 when the campus was raised to 1 gigawattMeta, Mar 26, 2026
- Development costAbout $14 billion for the buildings and long-lived power, cooling and connectivity infrastructure, per the July 2026 BlackRock ventureMeta, Jul 28, 2026
- JobsMore than 4,000 construction jobs at peak and more than 300 operating jobs. About 2,300 workers were already on site in July 2026.Meta, Jul 28, 2026
- WaterA closed-loop liquid-cooled system, with a pledge to restore 200% of the water the data center uses to local watershedsMeta, Mar 26, 2026
Next gate
Capacity starts coming online
2028
The Meta-BlackRock venture said it expects to begin bringing the campus's capacity online in 2028.
Every step so far, and what comes next
-
Done2025
Groundbreaking
Meta said in March 2026 that it had broken ground the year before.
Source: Meta, Mar 26, 2026
-
DoneMarch 26, 2026
Investment raised to more than $10 billion
Meta said the campus would grow to 1 gigawatt and that the investment would rise to more than $10 billion.
Source: Meta, Mar 26, 2026
-
DoneJuly 28, 2026
BlackRock venture announced
Meta and BlackRock announced a venture to finance the campus, with about 2,300 workers already on site.
Source: Meta, Jul 28, 2026
-
Next2028
Capacity starts coming online
The venture's published target.
Source: Meta, Jul 28, 2026
Worth knowing
- The map counts $10 billion plus, Meta's announced investment. The $14 billion figure is the venture's total development cost.
- Funds managed by BlackRock are to own 80% of the venture, with Meta retaining 20%.
- Dates are company targets.