Minnesota Energy Connection 345 kV transmission line
Under construction
About 174 miles of 345 kV line from southwest Minnesota to the Sherco grid connection near Becker, reusing coal plant interconnection for new wind and solar.
Show on the map: Minnesota Energy Connection
- Figure$1.274 billion (low end counted)Minnesota Public Utilities Commission, Jun 2025
- What gets builtAbout 174 miles of 345 kV line from southwest Minnesota to the Sherco grid connection near Becker, reusing coal plant interconnection for new wind and solarMinnesota Public Utilities Commission, Jun 2025
Next gate
Line energized
2028
Construction began in spring 2026, with energizing in 2028.
Every step so far, and what comes next
-
DoneJune 2025
Under construction
Construction began in spring 2026, with energizing in 2028.
-
Next2028
Line energized
Construction began in spring 2026, with energizing in 2028.
Worth knowing
- Pin at Becker; line runs to Lyon County.
Last checked Nov 28, 2026. We add a step when it happens and link the source.