Mississippi Crossing pipeline
A permitted, approximately $1.7 billion, nearly 208 mile natural gas pipeline and three compressor stations from near Greenville, Mississippi, to connections near Butler, Alabama, certificated by FERC on July 31, 2026 and expected in service as early as the second quarter of 2028.
Show on the map: Mississippi Crossing pipeline
- Investment and scopeKinder Morgan's official Mississippi Crossing project page, retrieved November 24, 2026, describes an approximately $1.7 billion project, the figure used on the map, designed to transport up to 2.1 billion cubic feet per day of natural gas through nearly 208 miles of 42-inch and 36-inch pipeline and laterals, plus three new compressor stations. The official page says the line will originate near Greenville, Mississippi, and connect to the existing Tennessee Gas Pipeline system and to Southern Natural Gas and Transco near Butler, Alabama. The pin is placed at the Mississippi origin; the route continues to Alabama and is not also pinned there.Kinder Morgan, Nov 24, 2026
- Certificate and scheduleThe same official page says Tennessee Gas Pipeline applied to the Federal Energy Regulatory Commission on June 30, 2025, that the final environmental impact statement was issued on June 26, 2026, and that FERC issued a certificate order authorizing the project on July 31, 2026, in Docket CP25-514-000. It says that, assuming timely receipt of all required permits and approvals, the project is expected to be placed in service as early as the second quarter of 2028. The official page reviewed this pass does not itself state that construction has begun. The map pin remains listed as permitted.Kinder Morgan, Nov 24, 2026
Next gate
In-service targeted as early as the second quarter of 2028, if remaining permits arrive on schedule
As early as the second quarter of 2028, according to the official project page retrieved November 24, 2026
The official Kinder Morgan project page, after recounting the July 31, 2026 FERC certificate, says the project is expected in service as early as the second quarter of 2028, assuming timely remaining permits and approvals. The page reviewed this pass does not itself state that construction has begun. The map pin remains listed as permitted.
Every step so far, and what comes next
-
DoneJune 26, 2026
FERC issues the final environmental impact statement
The official project page says the final EIS for Mississippi Crossing was issued on June 26, 2026.
Source: Kinder Morgan, Nov 24, 2026
-
DoneJuly 31, 2026
FERC issues a certificate authorizing the approximately $1.7 billion project
The official project page says FERC issued a certificate order authorizing the project on July 31, 2026, in Docket CP25-514-000, and describes the work as an approximately $1.7 billion project, the figure used on the map.
Source: Kinder Morgan, Nov 24, 2026
-
NextAs early as the second quarter of 2028, according to the official project page
In-service targeted, if remaining permits arrive on schedule
The official page expects the project to be placed in service as early as the second quarter of 2028, assuming timely remaining permits. The map pin remains listed as permitted.
Source: Kinder Morgan, Nov 24, 2026
Worth knowing
- The official cost is approximate. The $1.7 billion figure covers this single nearly 208-mile Tennessee Gas Pipeline project, including the three compressor stations.
- The official project page is a living page and is dated by retrieval on November 24, 2026. It records the July 31, 2026 certificate and does not itself state that construction has begun. The map pin remains listed as permitted, and this page does not change any map stage field.
- This pipeline is a separate project from other Kinder Morgan work in the region and is not added to any other pin.
Go deeper
Last checked Nov 24, 2026. We add a step when it happens and link the source.