I-10 Mobile River Bridge and Bayway, Phase One

Alabama Department of Transportation and Alabama Toll Road, Bridge and Tunnel Authority · I-10 across the Mobile River and Mobile Bay, Mobile and Baldwin counties, Alabama

Under construction

A $3.2 billion Phase One program for a new six-lane cable-stayed bridge and Bayway connections, with official groundbreaking in October 2026 and traffic projected in late 2031.

Show on the map: I-10 Mobile River Bridge and Bayway, Phase One

Next gate

New bridge and Phase One improvements projected to open to traffic

Late 2031

ALDOT's September 18, 2026 financing release said tolling would begin only when the new bridge and Phase One improvements open to traffic, currently projected for late 2031.

Every step so far, and what comes next

  1. DoneSeptember 18, 2026

    Financing closed for the $3.2 billion Phase One program

    The Alabama Toll Road, Bridge and Tunnel Authority completed bond and federal loan financing needed to fully fund Phase One construction.

  2. DoneOctober 2, 2026

    Official groundbreaking in Mobile

    State, federal, and local leaders broke ground at Cooper Riverside Park. ALDOT said the design-build team had begun mobilizing after a notice to proceed.

  3. NextLate 2031

    Phase One projected to open to traffic

    The opening window given in the September 18, 2026 ALDOT release.

Worth knowing

Last checked Nov 23, 2026. We add a step when it happens and link the source.