I-10 Mobile River Bridge and Bayway, Phase One
A $3.2 billion Phase One program for a new six-lane cable-stayed bridge and Bayway connections, with official groundbreaking in October 2026 and traffic projected in late 2031.
Show on the map: I-10 Mobile River Bridge and Bayway, Phase One
- Investment$3.2 billion, the figure used on the map, described by ALDOT as the agreed-upon Phase One construction cost, including a new six-lane cable-stayed bridge across the Mobile River and six lanes of capacity across the existing BaywayAlabama Department of Transportation, Sep 18, 2026
- ScopePhase One will build the new bridge, reconstruct about one mile of the Bayway to connect to it, restripe the existing Bayway to three travel lanes in each direction, and make interchange and corridor improvements in Mobile and Baldwin counties. Replacement of the rest of the Bayway is planned as a later phase and is not counted in the Phase One figureAlabama Department of Transportation, Sep 18, 2026
- ScheduleALDOT said financing closed on September 18, 2026, and that full construction was expected to be authorized beginning October 1. Officials broke ground on October 2, 2026. Traffic on the new bridge and Phase One improvements is currently projected for late 2031, about five years after construction start. No tolls will be collected during constructionAlabama Department of Transportation, Oct 2, 2026
Next gate
New bridge and Phase One improvements projected to open to traffic
Late 2031
ALDOT's September 18, 2026 financing release said tolling would begin only when the new bridge and Phase One improvements open to traffic, currently projected for late 2031.
Every step so far, and what comes next
-
DoneSeptember 18, 2026
Financing closed for the $3.2 billion Phase One program
The Alabama Toll Road, Bridge and Tunnel Authority completed bond and federal loan financing needed to fully fund Phase One construction.
-
DoneOctober 2, 2026
Official groundbreaking in Mobile
State, federal, and local leaders broke ground at Cooper Riverside Park. ALDOT said the design-build team had begun mobilizing after a notice to proceed.
-
NextLate 2031
Phase One projected to open to traffic
The opening window given in the September 18, 2026 ALDOT release.
Worth knowing
- The $3.2 billion figure is the Phase One design and construction cost. Financing tools described in the same release, including a $2.52 billion TIFIA loan, fund that construction cost and are not an additional construction budget on top of it.
- Replacement of the remainder of the Bayway is a later phase and is not included in the map figure.
- The late-2031 opening is the official projection and may move.
- The Wallace Tunnel, Bankhead Tunnel, Africatown Bridge, and Causeway are to remain toll-free alternatives.
Last checked Nov 23, 2026. We add a step when it happens and link the source.