Mountain Valley Pipeline
A 303-mile, 42-inch natural gas pipeline from northern West Virginia to southern Virginia, in service since June 14, 2024.
Show on the map: Mountain Valley Pipeline
- Investment$7.85 billion, the total project cost estimate including contingency and excluding financing costs during constructionEquitrans Midstream, via SEC, Apr 30, 2024
- CapacityUp to 2 billion cubic feet a day of firm transmission capacity, fully subscribed under 20-year contractsMountain Valley Pipeline / EQT, Nov 23, 2026
- RouteAbout 303 miles from Equitrans in Wetzel County, West Virginia, to Transco Station 165 in Pittsylvania County, Virginia, with three compressor stations in West VirginiaMountain Valley Pipeline / EQT, Nov 23, 2026
- OperatorEQT operates the pipeline and owns a significant interest in the joint venture with affiliates of NextEra Energy, AltaGas and RGC ResourcesMountain Valley Pipeline / EQT, Nov 23, 2026
Next gate
Commercial operation continues
In service since June 14, 2024
EQT's project overview says the pipeline entered service on June 14, 2024, and is operating under 20-year firm contracts for its full capacity. No further construction on this line is described there.
Every step so far, and what comes next
-
DoneApril 30, 2024
Cost estimate published
Equitrans' first-quarter 2024 results listed a $7.85 billion total project cost estimate, including contingency and excluding financing costs during construction.
-
DoneJune 14, 2024
Entered service
EQT says the Mountain Valley Pipeline system entered service on this date.
-
NextIn service since June 14, 2024
Commercial operation continues
The line is operating under 20-year firm contracts for its full capacity.
Worth knowing
- The pin is approximate, at the northern start near Mobley. The line runs into southern Virginia.
- The $7.85 billion figure is the last published total project cost estimate used on the map, from Equitrans' first-quarter 2024 results.
Last checked Nov 23, 2026. We add a step when it happens and link the source.