Naples Power Plant
An official Rural Utilities Service financial report certified April 30, 2026, says AECC began construction of the Naples Power Plant, a two-turbine simple-cycle natural gas plant of approximately 900 megawatts in Morris County, Texas, expected to enter commercial operation in the first quarter of 2029 at a total cost of $1,019 million.
Show on the map: Naples Power Plant
- Official cost, capacity, and construction statusThe official Rural Utilities Service Financial and Operating Report Electric Power Supply for Arkansas Electric Cooperative Corporation, borrower AR0034, for the period ended December 2025, certified by Vernon Hasten on April 30, 2026, and received by the Arkansas Public Service Commission audit section the same day, states that AECC began construction of the Naples Power Plant at a greenfield site in Morris County, Texas. It says the facility consists of two simple-cycle gas turbines with a proposed capacity of approximately 900 megawatts, and that the plant is expected to be commercially operational in the first quarter of 2029 at a total cost of $1,019 million. The official $1,019 million total cost is the amount used on the map.Arkansas Electric Cooperative Corporation (filed with USDA Rural Utilities Service and the Arkansas Public Service Commission), Apr 30, 2026
Next gate
Official April 30, 2026 report said the plant is expected to enter commercial operation in the first quarter of 2029
After the official report's statement that construction has begun, toward the official first-quarter 2029 commercial operation
The official certified report says AECC began construction of the approximately 900-megawatt Naples Power Plant in Morris County at a total cost of $1,019 million, with commercial operation expected in the first quarter of 2029. The map pin remains listed as under construction.
Every step so far, and what comes next
-
DoneOn or before the December 2025 reporting period, as certified April 30, 2026
AECC reports that construction of the Naples Power Plant has begun
The official certified report states that AECC began construction of the two-turbine, approximately 900-megawatt simple-cycle plant at a greenfield site in Morris County, Texas, at a total cost of $1,019 million, with commercial operation expected in the first quarter of 2029.
-
NextAfter the official report's statement that construction has begun, toward the official first-quarter 2029 commercial operation
Official April 30, 2026 report said the plant is expected to enter commercial operation in the first quarter of 2029
The official certified report says AECC began construction of the approximately 900-megawatt Naples Power Plant in Morris County at a total cost of $1,019 million, with commercial operation expected in the first quarter of 2029. The map pin remains listed as under construction.
Worth knowing
- The map figure is the official total cost of $1,019 million stated in AECC's Rural Utilities Service financial report for the period ended December 2025, certified April 30, 2026. This page does not change any map usd, stage, or pledge field.
- The same official report also describes other AECC generation projects, including a Fitzhugh generation addition and a separate project with a projected cost of $1,350 million. Those are not included in this pin. This is also a separate project from IGP 3-6.
Go deeper
Last checked Nov 24, 2026. We add a step when it happens and link the source.