Newark Bay Bridge replacement, NJ Turnpike Extension
A new cable-stayed span to replace the Vincent R. Casciano Bridge on the Turnpike's Newark Bay-Hudson County Extension.
Show on the map: Newark Bay Bridge replacement, NJ Turnpike Extension
- Investment$6.7 billion for the Newark Bay Bridge program, the figure used on the map, from Governor Mikie Sherrill's March 3, 2026 statement. The governor called it the largest single project the Turnpike Authority has advancedOffice of the Governor of New Jersey, Mar 3, 2026
- Full program costThe Turnpike Authority's program FAQ estimates the entire 8.1-mile Newark Bay-Hudson County Extension Improvements Program, which would replace all 29 bridges on the Extension, at $10.7 billion, paid entirely from Turnpike toll revenue, with no local, county, state, or federal tax dollarsNew Jersey Turnpike Authority, Nov 23, 2026
- DesignThe governor recommended immediate construction of a four-lane bridge with shouldersOffice of the Governor of New Jersey, Mar 3, 2026
- LanesThe Authority's FAQ says Project 1 will add two lanes in each direction between Interchanges 14 and 14A, and will not add lanes between Interchange 14A and Jersey AvenueNew Jersey Turnpike Authority, Nov 23, 2026
- JobsApproximately 19,000 jobs, including thousands of union construction jobs, according to the governor's March 3, 2026 statementOffice of the Governor of New Jersey, Mar 3, 2026
- ContractsThe Authority's capital projects page says the first contracts for the new cable-stayed bridge were awarded in spring 2026New Jersey Turnpike Authority, Nov 23, 2026
- ProgressThe official Project 1 page says construction of in-water trestles from each side of Newark Bay began in summer 2026, with no impact to traffic on the ExtensionNew Jersey Turnpike Authority, Nov 23, 2026
Next gate
Construction of the new cable-stayed bridge
Anticipated to begin in 2027
An April 2026 Authority notice said the main contract for the new cable-stayed bridge, to be built on the west side of Newark Bay beside the existing span, was expected to be awarded in 2027 after prequalification, with construction anticipated to begin in 2027.
Every step so far, and what comes next
-
DoneMarch 3, 2026
Governor recommends $6.7 billion program
Governor Sherrill recommended that the Turnpike Authority Board advance the $6.7 billion Newark Bay Bridge program, with traffic expected to shift off the existing bridge by 2031.
-
DoneApril 2026
Main bridge contract notice issued
The Authority issued a notice of intent to seek qualified contractors for the new cable-stayed bridge. Award was expected in 2027.
-
DoneSpring 2026
First construction contracts awarded
The Authority's capital projects page says the first contracts for construction of the new cable-stayed bridge over Newark Bay were awarded in the spring of 2026.
-
DoneSummer 2026
In-water trestle construction began
The official Project 1 page says construction of in-water trestles, extending from each side of Newark Bay, began in summer 2026, with no impact to traffic on the Extension.
-
Next2027
Construction of the new cable-stayed bridge
The April 2026 notice said construction of the new span was anticipated to begin in 2027, after the main contract is awarded.
-
Expected2031
Traffic shifts to the new bridge
The Authority's capital projects page says the bridge is expected to be completed and opened to traffic in 2031, after which the existing bridge would be demolished.
Worth knowing
- The map counts the governor's $6.7 billion figure for the Newark Bay Bridge program. The Authority's FAQ quotes $10.7 billion for the full 8.1-mile, 29-bridge program. This page keeps the map figure and lists the official full-program estimate separately.
- Official completion dates differ. The governor's March 2026 statement and the Authority's capital projects page say traffic is expected to shift to the new bridge in 2031, after which the existing bridge would be demolished. The April 2026 contract notice also used a 2031 completion goal. The current Project 1 schedule page gives an anticipated completion goal of 2032.
- Some later news reports have cited about $6.8 billion. This page uses the official $6.7 billion and $10.7 billion figures only.
- A November 2026 groundbreaking date has appeared in news coverage. This page does not use that date, because it was not found on the official governor or Turnpike Authority pages checked on Nov 23, 2026.
Last checked Nov 23, 2026. We add a step when it happens and link the source.