North Houston Highway Improvement Project (I-45)

Texas Department of Transportation · Downtown Houston north toward Beltway 8, Harris County, Texas

Under construction

Rebuilding I-45 and the downtown Houston freeway loop, with the first drainage and I-69 segments already under construction.

Show on the map: North Houston Highway Improvement Project (I-45)

Next gate

Alabama Street bridge reconstructed

February 2027

TxDOT says reconstruction of the Alabama Street bridge over I-69 and SH 288 is scheduled to finish in February 2027, after demolition that began in 2026.

Every step so far, and what comes next

  1. DoneOct 28, 2024

    Construction begins

    TxDOT broke ground and started Segment 3B-1, the first drainage work east of downtown.

  2. DoneJanuary 2025

    Segment 3B-2 begins

    Construction started on the I-69 mainlanes from SH 288 to I-45.

  3. Done2026

    Alabama Street bridge demolished

    TxDOT said crews completed demolition of the Alabama Street bridge over I-69. Mainlane work on 3B-2 had begun in May.

  4. NextFebruary 2027

    Alabama Street bridge reconstructed

    Scheduled completion for the new bridge, from April 30, 2026, to February 8, 2027.

  5. ExpectedEarly 2028

    Segment 3B-1 complete

    TxDOT's anticipated completion for the first drainage project.

  6. Expected2033

    Segment 3B-2 complete

    TxDOT's anticipated completion for the I-69 widening now under way.

Worth knowing

Last checked Nov 23, 2026. We add a step when it happens and link the source.