North Houston Highway Improvement Project (I-45)
Rebuilding I-45 and the downtown Houston freeway loop, with the first drainage and I-69 segments already under construction.
Show on the map: North Houston Highway Improvement Project (I-45)
- Program cost$13 billion, the figure TxDOT used at the Oct 2024 groundbreakingTexas Department of Transportation, Oct 28, 2024
- ScopeI-45 from downtown Houston north to Beltway 8, plus rebuilding the downtown loop of I-45, I-69, I-10 and SH 288Texas Department of Transportation, Oct 28, 2024
- Segment 3B-1A $121.8 million drainage project that began in October 2024, aimed at early 2028, including a detention pond of nearly 76 million gallonsTexas Department of Transportation, Oct 21, 2026
- Segment 3B-2A $695.5 million rebuild and widening of I-69 from SH 288 to I-45, begun in January 2025 and aimed at 2033Texas Department of Transportation, Oct 30, 2026
Next gate
Alabama Street bridge reconstructed
February 2027
TxDOT says reconstruction of the Alabama Street bridge over I-69 and SH 288 is scheduled to finish in February 2027, after demolition that began in 2026.
Every step so far, and what comes next
-
DoneOct 28, 2024
Construction begins
TxDOT broke ground and started Segment 3B-1, the first drainage work east of downtown.
-
DoneJanuary 2025
Segment 3B-2 begins
Construction started on the I-69 mainlanes from SH 288 to I-45.
-
Done2026
Alabama Street bridge demolished
TxDOT said crews completed demolition of the Alabama Street bridge over I-69. Mainlane work on 3B-2 had begun in May.
-
NextFebruary 2027
Alabama Street bridge reconstructed
Scheduled completion for the new bridge, from April 30, 2026, to February 8, 2027.
-
ExpectedEarly 2028
Segment 3B-1 complete
TxDOT's anticipated completion for the first drainage project.
-
Expected2033
Segment 3B-2 complete
TxDOT's anticipated completion for the I-69 widening now under way.
Worth knowing
- $13 billion is the 2024 program figure for the full multi-segment project, not a current bid total for every contract.
- Only some Segment 3 contracts are under construction. Later downtown and northside segments have not started.
- The pin is at downtown Houston.
- The 2024 groundbreaking release said the whole project would take 18 years.
Last checked Nov 23, 2026. We add a step when it happens and link the source.