North Plains Connector HVDC transmission line
A bidirectional high-voltage direct current line meant to link the Eastern and Western grids, still in permitting.
Show on the map: North Plains Connector HVDC transmission line
- InvestmentApproximately $6 billion for the entire project, the figure used on the map and on the developer's site. The North Dakota Public Service Commission has said the North Dakota portion is estimated at about $3.2 billionNorth Plains Connector (Grid United and ALLETE), Nov 23, 2026
- ScopeThe developer's site describes a 420-mile, up-to-525-kilovolt HVDC line from an existing substation in Colstrip to two North Dakota connections, near Center and St. AnthonyNorth Plains Connector (Grid United and ALLETE), Nov 23, 2026
- CapacityMontana DEQ's August 28, 2026 Final EIS notice said the line would carry 525 kilovolts of high-voltage direct current and provide 3,000 megawatts connecting the Western electrical grid to Eastern statesMontana Department of Environmental Quality, Aug 28, 2026
- North Dakota lengthThe August 18, 2026 PSC notice described about 168 miles of HVDC line and about 74 miles of associated 345-kV lines in North Dakota, and said the entire line would extend about 422 milesNorth Dakota Public Service Commission, Aug 18, 2026
- Montana reviewOn August 28, 2026, Montana DEQ issued a Final Environmental Impact Statement. DEQ said a Major Facility Siting Act certificate is required before construction can begin, and that it had to wait 15 days after the Final EIS to issue a record of decision and certificateMontana Department of Environmental Quality, Aug 28, 2026
- North Dakota reviewThe PSC held a technical hearing on September 1, 2026, and public hearings on September 2 and 3. Case PU-26-082 was still listed as open, with no closed date, on the commission's case page checked on Nov 23, 2026North Dakota Public Service Commission, Nov 23, 2026
Next gate
Remaining siting approvals
The developer has said approvals are expected in late 2026
The project homepage says North Plains Connector is in the permitting phase, with regulatory approvals expected in late 2026. Major construction is expected to start in 2028, with commercial operation expected in 2032.
Every step so far, and what comes next
-
DoneAugust 18, 2026
North Dakota hearings scheduled
The PSC scheduled September hearings on a siting permit for the North Dakota portion and published a $6 billion total and $3.2 billion North Dakota cost estimate.
Source: North Dakota Public Service Commission, Aug 18, 2026
-
DoneAugust 28, 2026
Montana Final EIS issued
Montana DEQ, with the U.S. Department of Energy as co-lead, issued a Final EIS and said a siting certificate is required before construction.
Source: Montana Department of Environmental Quality, Aug 28, 2026
-
DoneSeptember 1 to 3, 2026
North Dakota hearings held
The PSC case page records a technical hearing on September 1 and public hearings on September 2 and 3. The case remained open when checked on Nov 23, 2026.
Source: North Dakota Public Service Commission, Nov 23, 2026
-
NextLate 2026
Remaining siting approvals
The developer homepage says regulatory approvals are expected in late 2026.
Source: North Plains Connector (Grid United and ALLETE), Nov 23, 2026
-
Expected2028
Major construction start
The developer homepage says major construction activities are expected to commence in 2028, with commercial operation expected in 2032.
Source: North Plains Connector (Grid United and ALLETE), Nov 23, 2026
Worth knowing
- Official length figures differ slightly: about 420 miles on the developer site and about 422 miles in the North Dakota PSC notice.
- The 3,000 megawatt figure is from Montana DEQ's Final EIS notice. The developer homepage describes capacity in voltage terms (up to 525 kilovolts) and does not repeat a megawatt rating in the text checked for this pass.
- This page does not treat the Montana certificate or the North Dakota siting permit as granted. The Montana Final EIS notice said a certificate still had to follow, and the North Dakota case page was still open when checked.
- The line crosses two states. The map pin is at the Colstrip end.