Track your favorite projects · Transmission

North Plains Connector HVDC transmission line

North Plains Connector LLC (Grid United and ALLETE) · From near Colstrip, Montana, to Center and St. Anthony, North Dakota (map pin at the Colstrip end)

Permitting

A bidirectional high-voltage direct current line meant to link the Eastern and Western grids, still in permitting.

Show on the map: North Plains Connector HVDC transmission line

Next gate

Remaining siting approvals

The developer has said approvals are expected in late 2026

The project homepage says North Plains Connector is in the permitting phase, with regulatory approvals expected in late 2026. Major construction is expected to start in 2028, with commercial operation expected in 2032.

Every step so far, and what comes next

  1. DoneAugust 18, 2026

    North Dakota hearings scheduled

    The PSC scheduled September hearings on a siting permit for the North Dakota portion and published a $6 billion total and $3.2 billion North Dakota cost estimate.

  2. DoneAugust 28, 2026

    Montana Final EIS issued

    Montana DEQ, with the U.S. Department of Energy as co-lead, issued a Final EIS and said a siting certificate is required before construction.

  3. DoneSeptember 1 to 3, 2026

    North Dakota hearings held

    The PSC case page records a technical hearing on September 1 and public hearings on September 2 and 3. The case remained open when checked on Nov 23, 2026.

  4. NextLate 2026

    Remaining siting approvals

    The developer homepage says regulatory approvals are expected in late 2026.

  5. Expected2028

    Major construction start

    The developer homepage says major construction activities are expected to commence in 2028, with commercial operation expected in 2032.

Worth knowing

Go deeper

Last checked Nov 23, 2026. We add a step when it happens and link the source.

Tracking saves to this device only. No account, no email, free.