Novva West Jordan data center campus
Under construction
A 175 MW, one-million-square-foot campus in West Jordan cooled without water.
Show on the map: Novva West Jordan
- Figure$2 billion (financing)CIM Group, Mar 5, 2025
- What gets builtA 175 MW, one-million-square-foot campus in West Jordan cooled without waterCIM Group, Mar 5, 2025
Next gate
SLC West final completion
January 2027 (rating report)
HR Ratings reports final completion of the third building expected in January 2027.
Every step so far, and what comes next
-
DoneJuly 16, 2026
Two buildings operating
HR Ratings reports SLC North and SLC East operating and the project 78.9% complete.
Source: HR Ratings, Jul 16, 2026
-
NextJanuary 2027 (rating report)
SLC West final completion
HR Ratings reports final completion of the third building expected in January 2027.
Source: CIM Group, Mar 5, 2025
Worth knowing
- Figure is the $2 billion financing from J.P. Morgan and Starwood Property Trust for phases 2 and 3, not a construction cost. HR Ratings (July 16, 2026) puts the total project budget at $2,433.7 million.
- Stage is under construction: the first two buildings are operating, and HR Ratings reports the third (SLC West) and a new substation still under construction, with final completion expected in January 2027.
- Pin is approximate, at 6477 Wells Park Road, West Jordan.
Last checked Nov 28, 2026. We add a step when it happens and link the source.