NPPD Princeton Road Station gas plant, Phase 1, Lancaster County
A $3.1 billion Phase 1 natural gas plant, including transmission costs, with official groundbreaking in July 2026 and a summer 2029 in-service target.
Show on the map: NPPD Princeton Road Station gas plant, Phase 1, Lancaster County
- Investment$3.1 billion estimated total cost for Phase 1, the figure used on the map, from NPPD's Planned Generation Key Facts sheet, which says that total includes transmission costsNebraska Public Power District, Nov 23, 2026
- ScopePhase 1 is 12 reciprocating internal combustion engines totaling 216 megawatts of summer capacity and two combustion turbines totaling 478 megawatts, or 694 megawatts in all. NPPD's July 17, 2026 groundbreaking release said that is enough to serve an estimated 318,000 average residential homes, and that the plant can also use diesel fuelNebraska Public Power District, Nov 23, 2026
- ScheduleNPPD celebrated an official groundbreaking on July 17, 2026, just north of Hallam. The official project page says construction has begun, and the Key Facts sheet targets Phase 1 in service in summer 2029. A separate Phase 2 of three more combustion turbines, estimated at $1.8 billion including transmission, is targeted for 2032 and is not included in the map figureNebraska Public Power District, Jul 17, 2026
Next gate
Phase 1 targeted to enter service
Summer 2029
The official Key Facts sheet lists a summer 2029 in-service target for Phase 1. The July 17, 2026 groundbreaking release said the station is anticipated to begin operating in 2029.
Every step so far, and what comes next
-
DoneJuly 17, 2026
Official groundbreaking just north of Hallam
NPPD celebrated the start of construction on Princeton Road Station, described as the largest natural gas generation facility in its fleet.
-
NextSummer 2029
Phase 1 targeted to enter service
The in-service window given on NPPD's Planned Generation Key Facts sheet.
-
Expected2032
Phase 2 targeted, not included in the map figure
The Key Facts sheet lists Phase 2 in-service targets in June and December 2032.
Worth knowing
- The $3.1 billion Phase 1 figure officially includes transmission costs. Phase 2, estimated at $1.8 billion including transmission and targeted for 2032, is not counted on the map.
- The 2029 in-service date is an official target and may move.
- The pin is approximate, north of Hallam next to Sheldon Station.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.