Nucor Steel West Virginia sheet mill, Apple Grove
A 3-million-ton-a-year sheet mill that poured its first heat in September 2026. The map counts Nucor's 2023 $3.1 billion net cash outlay estimate; the company's current West Virginia page describes a $4 billion investment.
Show on the map: Nucor Steel West Virginia sheet mill, Apple Grove
- Map figureApproximately $3.1 billion in net cash outlay, the figure used on the map, from Nucor's February 23, 2023 update, up from $2.7 billion when the project was announced in September 2021. That 2023 estimate was net of $275 million in cash proceeds from the State of West Virginia for costs related to the Apple Grove siteNucor, Feb 23, 2023
- Scope and jobsThe 2023 update said the mill will have an annual capacity of 3 million tons and employ about 800 full-time teammates when fully operational, plus as many as 2,000 construction workers during the building phase. Nucor's current West Virginia page also lists a 1,700-acre site and a high-end automotive galvanizing and construction lineNucor, Feb 23, 2023
- First heatIn its October 26, 2026 third-quarter results, Nucor said it achieved the first heat at the West Virginia sheet mill in September 2026Nucor, Oct 26, 2026
Next gate
Continue commissioning after the first heat and ramp toward full operation
After the September 2026 first heat; the official third-quarter release did not give a later commercial-production date
Nucor has officially confirmed the first heat. This page does not assign a later official start-of-production date that was not stated in that October 26, 2026 release.
Every step so far, and what comes next
-
DoneFebruary 23, 2023
Nucor raises the net cash outlay estimate to about $3.1 billion
The company said the Board approved additional capital and raised the estimate from $2.7 billion, net of $275 million in state proceeds.
Source: Nucor, Feb 23, 2023
-
DoneSeptember 2026
First heat at the West Virginia sheet mill
Nucor's October 26, 2026 earnings release reported the first heat in September.
Source: Nucor, Oct 26, 2026
-
NextAfter the first heat
Continue commissioning and ramp toward full operation
No later official commercial-production date was given in the October 26, 2026 release.
Source: Nucor, Oct 26, 2026
Worth knowing
- The map counts the approximately $3.1 billion net cash outlay Nucor published in February 2023. The company's current West Virginia page describes a $4 billion investment. This page does not replace the map figure with that later website wording.
- The $3.1 billion 2023 figure is net of $275 million in state proceeds.
- First heat is a steelmaking milestone. It is not, by itself, the same as full commercial production.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.