Ocean Terminal renovation, Port of Savannah
A $1.6 billion renovation of the Port of Savannah's Ocean Terminal, officially more than 60 percent complete as of September 29, 2026, raising annual container capacity from 200,000 twenty-foot equivalent units to 1.75 million TEUs.
Show on the map: Ocean Terminal renovation, Port of Savannah
- Investment and progressAn official September 29, 2026 Georgia Ports Authority news release says renovations at the Port of Savannah's Ocean Terminal are more than 60 percent complete. The official release says the $1.6 billion project, the figure used on the map, will grow the facility's annual container capacity from 200,000 twenty-foot equivalent units to 1.75 million TEUs. It also says a 2,650-foot berth is completed and working ships, and that the truck gate is fully operational.Georgia Ports Authority, Sep 29, 2026
- ScheduleThe official release says GPA will work smaller vessels at Ocean Terminal until mid-fall 2027, when the first phase of the container yard renovation is complete, and that the entire Ocean Terminal yard will be completed by the end of 2028.Georgia Ports Authority, Sep 29, 2026
Next gate
First container-yard phase due in mid-fall 2027, with the full yard scheduled by the end of 2028
Mid-fall 2027 and the end of 2028, according to the official September 29, 2026 GPA release
The official release schedules the first phase of the container-yard renovation for mid-fall 2027 and completion of the entire yard by the end of 2028. The map pin remains listed as under construction.
Every step so far, and what comes next
-
DoneSeptember 29, 2026
Authority says the $1.6 billion renovation is more than 60 percent complete
The official GPA release said the $1.6 billion Ocean Terminal renovation, the figure used on the map, was more than 60 percent complete, with a 2,650-foot berth finished and working ships and the truck gate in operation.
-
NextMid-fall 2027 for the first yard phase, and the end of 2028 for the full yard, according to the official release
First container-yard phase, then completion of the full yard
The official release schedules those remaining yard milestones. The map pin remains listed as under construction.
Worth knowing
- The map figure is the official $1.6 billion project cost in GPA's September 29, 2026 update.
- A $29 million port-funded overpass mentioned in the same official release, and GPA's broader multi-year port investment plan, are not used to replace or enlarge this project's official total.
- The official release says the renovation was already more than 60 percent complete. The map pin remains listed as under construction, and this page does not change any map stage field.
Last checked Nov 24, 2026. We add a step when it happens and link the source.