Ohio River Tunnel

Allegheny County Sanitary Authority · Pittsburgh and McKees Rocks, Allegheny County, Pennsylvania

Under construction

Official ALCOSAN records award Contract No. 1797, the Ohio River Tunnel, at $1,086,294,397.65, and an official June 1, 2026 notice to proceed authorized construction to begin that day, with completion scheduled for late 2032.

Show on the map: Ohio River Tunnel

Next gate

Official June 1, 2026 notice authorized construction through late 2032

After the official June 1, 2026 notice to proceed, toward the official late 2032 completion

The official ALCOSAN notice authorized construction to begin June 1, 2026, and said the Ohio River Tunnel is scheduled to end in late 2032. The official project page, retrieved November 24, 2026, likewise anticipates completion by the end of 2032. The map pin remains listed as under construction.

Every step so far, and what comes next

  1. DoneApril 16, 2026

    ALCOSAN Board agenda includes the award of Contract No. 1797

    The official board agenda lists a motion to award the Ohio River Tunnel contract to Brayman-Lane JV at $1,086,294,397.65, including a $1,034,566,093.00 base bid and a 5 percent contingency.

  2. DoneJune 1, 2026

    ALCOSAN issues a notice to proceed

    The official notice said work was authorized to begin June 1, 2026, and that construction is scheduled for 6 years and 5 months, ending in late 2032.

  3. NextAfter the official June 1, 2026 notice to proceed, toward the official late 2032 completion

    Official June 1, 2026 notice authorized construction through late 2032

    The official ALCOSAN notice authorized construction to begin June 1, 2026, and said the Ohio River Tunnel is scheduled to end in late 2032. The official project page, retrieved November 24, 2026, likewise anticipates completion by the end of 2032. The map pin remains listed as under construction.

Worth knowing

Go deeper

Last checked Nov 24, 2026. We add a step when it happens and link the source.