Ohio River Tunnel
Official ALCOSAN records award Contract No. 1797, the Ohio River Tunnel, at $1,086,294,397.65, and an official June 1, 2026 notice to proceed authorized construction to begin that day, with completion scheduled for late 2032.
Show on the map: Ohio River Tunnel
- Official award priceThe official April 16, 2026 agenda for a regular meeting of the ALCOSAN Board includes a motion to award Contract No. 1797, Ohio River Tunnel, to Brayman-Lane JV at the price of $1,086,294,397.65, which includes the base contract bid of $1,034,566,093.00 and a 5 percent contingency of $51,728,304.65. The official award price, rounded to the nearest dollar, is the amount used on the map.Allegheny County Sanitary Authority, Apr 16, 2026
- Official notice to proceed and scheduleThe official June 1, 2026 ALCOSAN notice says the authority issued a notice to proceed for the Ohio River Tunnel, the first part of the Regional Tunnel System, and that work was officially authorized to begin Monday, June 1, 2026. It says construction is scheduled for 6 years and 5 months, beginning that day and ending in late 2032. The official notice identifies the contractor as Steel City Tunnel Partners, an equal partnership between The Lane Construction Corporation and Brayman Construction Corporation, and says the joint venture was awarded the contract at ALCOSAN's April 2026 board meeting. The same official notice refers to the award as an approximately $1 billion contract; that rounded wording is not used to replace the official award price.Allegheny County Sanitary Authority, Jun 1, 2026
- Official length and routeThe official ALCOSAN Ohio River Tunnel project page, retrieved November 24, 2026, lists a total length of 4.9 miles and construction sites of 6 in the City of Pittsburgh and 2 in McKees Rocks Borough. It describes a main tunnel roughly 18 feet in diameter and 3.8 miles long, running from the North Shore near the Veterans Bridge to the new pump station and the treatment plant near the McKees Rocks Bridge, with smaller tunnels capturing flows from the Saw Mill Run and Chartiers Creek areas. The official page says notice to proceed was issued to the contractor on June 1, 2026, and that construction is anticipated to be completed by the end of 2032.Allegheny County Sanitary Authority, Nov 24, 2026
Next gate
Official June 1, 2026 notice authorized construction through late 2032
After the official June 1, 2026 notice to proceed, toward the official late 2032 completion
The official ALCOSAN notice authorized construction to begin June 1, 2026, and said the Ohio River Tunnel is scheduled to end in late 2032. The official project page, retrieved November 24, 2026, likewise anticipates completion by the end of 2032. The map pin remains listed as under construction.
Every step so far, and what comes next
-
DoneApril 16, 2026
ALCOSAN Board agenda includes the award of Contract No. 1797
The official board agenda lists a motion to award the Ohio River Tunnel contract to Brayman-Lane JV at $1,086,294,397.65, including a $1,034,566,093.00 base bid and a 5 percent contingency.
-
DoneJune 1, 2026
ALCOSAN issues a notice to proceed
The official notice said work was authorized to begin June 1, 2026, and that construction is scheduled for 6 years and 5 months, ending in late 2032.
-
NextAfter the official June 1, 2026 notice to proceed, toward the official late 2032 completion
Official June 1, 2026 notice authorized construction through late 2032
The official ALCOSAN notice authorized construction to begin June 1, 2026, and said the Ohio River Tunnel is scheduled to end in late 2032. The official project page, retrieved November 24, 2026, likewise anticipates completion by the end of 2032. The map pin remains listed as under construction.
Worth knowing
- The map figure is the official award price of $1,086,294,397.65 for Contract No. 1797 in ALCOSAN's April 16, 2026 board agenda, rounded to the nearest dollar on the map. The official 5 percent contingency is included in that award price. This page does not change any map usd, stage, or pledge field.
- The official June 1, 2026 notice's rounded reference to an approximately $1 billion contract is not used to replace the official award price.
- The Ohio River Tunnel is the first of three planned regional tunnels. Official references to the broader Clean Water Plan and to a full tunnel system of more than 16 miles are not added to this pin.