ORDNext O'Hare modernization program
An $8.8 billion program to rebuild the heart of O'Hare, including new concourses and the O'Hare Global Terminal.
Show on the map: ORDNext O'Hare modernization program
- Program cost$8.8 billionCity of Chicago, Aug 20, 2026
- Concourse EA $917 million, 24-gate concourse in two phases: a $640 million first phase with 14 gates, targeted for 2030, and a $277 million second phase with 10 more gates in 2034City of Chicago, Nov 17, 2026
- Concourse DA 19-gate concourse with a guaranteed maximum price of $1.455 billion, $21 million below its initially approved budget, scheduled for completion in late 2028. Vertical construction is under wayCity of Chicago, Nov 17, 2026
- Global TerminalScheduled to begin construction in 2029 and be delivered in a single phase by late 2033City of Chicago, Nov 17, 2026
- CapacityWhen complete, the program is expected to increase O'Hare's gate capacity by about 14%City of Chicago, Nov 17, 2026
Next gate
New Concourse D complete
Late 2028
The city says The New Concourse D remains scheduled for completion in late 2028, with the first 14 Concourse E gates targeted for 2030.
Every step so far, and what comes next
-
DoneAug 20, 2026
Concourse E phasing announced
The city said it would break ground later in 2026 on the first phase of The New Concourse E and laid out a sequence to the Global Terminal.
Source: City of Chicago, Aug 20, 2026
-
DoneNov 17, 2026
Concourse E groundbreaking
Mayor Johnson and the Chicago Department of Aviation broke ground on the $917 million New Concourse E.
Source: City of Chicago, Nov 17, 2026
-
NextLate 2028
New Concourse D complete
The 19-gate concourse is scheduled for completion in late 2028.
Source: City of Chicago, Nov 17, 2026
-
Expected2030
Concourse E first 14 gates
The $640 million first phase is targeted for completion in 2030.
Source: City of Chicago, Nov 17, 2026
-
ExpectedLate 2033
O'Hare Global Terminal
Construction is scheduled to start in 2029, with delivery in a single phase by late 2033.
Source: City of Chicago, Nov 17, 2026
-
Expected2034
Concourse E completed
The second phase is scheduled to add 10 gates after the Global Terminal, bringing Concourse E to 24 gates in 2034.
Source: City of Chicago, Nov 17, 2026
Worth knowing
- ORDNext is built in phases. The $8.8 billion figure is the program total, not the cost of a single building.
- Dates are city targets and can change.
Last checked Nov 23, 2026. We add a step when it happens and link the source.