Palisades Nuclear Plant restart, Covert Township
A restart of the 800 megawatt Palisades Nuclear Plant on Lake Michigan, which ceased operations in May 2022, backed by an official $1.52 billion Department of Energy loan closed in September 2024.
Show on the map: Palisades Nuclear Plant restart, Covert Township
- Official loan and projectThe official U.S. Department of Energy Palisades page, last updated October 29, 2026, says that in September 2024 the department announced the closing of a $1.52 billion loan to Holtec Palisades, LLC to help finance the restoration and restart of the 800 megawatt Palisades Nuclear Plant in Covert Township, Michigan. That official loan amount is the figure used on the map. The official page says the plant ceased operations in May 2022 and will be brought back online and upgraded to produce firm baseload power until at least 2051, subject to U.S. Nuclear Regulatory Commission licensing approvals.U.S. Department of Energy, Oct 29, 2026
- Official description of the loan's roleThe same official DOE page describes the $1.52 billion loan as support to help finance the restoration and restart. The official page does not state a separate full project cost, and none is invented here. The map pin remains listed as commissioning.U.S. Department of Energy, Oct 29, 2026
Next gate
Restart remains subject to NRC licensing approvals
As described on the official DOE page last updated October 29, 2026
The official DOE page says the plant will be brought back online and upgraded to produce power until at least 2051, subject to NRC licensing approvals. The map pin remains listed as commissioning.
Every step so far, and what comes next
-
DoneSeptember 2024, according to the official DOE page last updated October 29, 2026
DOE announces closing of a $1.52 billion loan to help finance the restart
The official DOE Palisades page said the department closed a $1.52 billion loan to Holtec Palisades, LLC to help finance the restoration and restart of the 800 megawatt plant, the figure used on the map.
-
NextAs described on the official DOE page last updated October 29, 2026
Restart remains subject to NRC licensing approvals
The official page says the plant will be brought back online and upgraded to produce power until at least 2051, subject to NRC licensing approvals. The map pin remains listed as commissioning.
Worth knowing
- The map figure is the official $1.52 billion Department of Energy loan closed in September 2024, as stated on the official DOE Palisades page last updated October 29, 2026. The official page says the loan is to help finance the restart and does not itself state a separate full project total. This page does not invent one, and it does not use the loan to imply a different official project cost.
- Expected job figures on the official DOE page are not added to the map total.
- The map pin remains listed as commissioning, and this page does not change any map stage field.