Pearl Harbor Naval Shipyard Dry Dock 5
A new concrete dry dock replacing Dry Dock 3, awarded at $2.84 billion in March 2023, under construction, and expected to be completed by September 2027.
Show on the map: Pearl Harbor Naval Shipyard Dry Dock 5
- InvestmentOn March 10, 2023, the Defense Department announced a $2,839,880,250 firm-fixed-price task order to Dragados/Hawaiian Dredging/Orion JV for construction of a concrete dry dock at Pearl Harbor Naval Shipyard, the figure rounded to $2.84 billion on the map. Work was expected to be completed by September 2027. The award also contained three unexercised options that, if exercised, would raise the cumulative contract value to $3,417,092,900; those options are not included in the map figureU.S. Department of Defense, Mar 10, 2023
- ScopeNAVFAC Pacific said the planned five-year project will construct a graving dock, to be designated Dry Dock 5, replacing Dry Dock 3 as part of the Navy's Shipyard Infrastructure Optimization Program, so the shipyard can continue maintaining and modernizing the Pacific Fleet's nuclear-powered submarinesNaval Facilities Engineering Systems Command, Mar 10, 2023
- Construction progressA November 28, 2025 NAVFAC release described a November 21, 2025 site tour of the future Dry Dock 5 by the Chief of Naval Operations, including transport of nine 4,600-ton precast floor units from Waipio Peninsula. A later official U.S. Navy DVIDS account, accompanied by a September 23, 2026 aerial photo, described the project as building toward dewatering of the cofferdam so crews can construct the permanent wallsNaval Facilities Engineering Systems Command, Nov 28, 2025
Next gate
Contract completion targeted
September 2027
The March 10, 2023 contract announcement said work is expected to be completed by September 2027. Official 2026 Navy materials describe the next major construction transition as dewatering, without changing that contract completion date.
Every step so far, and what comes next
-
DoneMarch 10, 2023
Task order awarded at $2.84 billion
The Defense Department announced the firm-fixed-price task order, with work expected to be completed by September 2027.
-
DoneNovember 21, 2025
Chief of Naval Operations toured the construction site
NAVFAC described an official site tour that included ongoing transport of precast floor units to the Dry Dock 5 site.
Source: Naval Facilities Engineering Systems Command, Nov 28, 2025
-
DoneAs described with a September 23, 2026 official aerial photo
Construction described as building toward dewatering
A U.S. Navy DVIDS account said the next major transition is dewatering the cofferdam so permanent walls can be built.
Source: U.S. Navy / DVIDS, Sep 23, 2026
-
NextSeptember 2027
Expected contract completion
The March 10, 2023 official contract announcement said work is expected to be completed by September 2027.
Worth knowing
- The map figure is the $2,839,880,250 task order as awarded, rounded to $2.84 billion. Unexercised options that could raise the cumulative value to $3,417,092,900 are not counted.
- A later unofficial or social-media completion-percentage figure was not used. Construction status is taken from official NAVFAC and U.S. Navy DVIDS materials.
Last checked Nov 23, 2026. We add a step when it happens and link the source.