Person County CC1
A 1,365 megawatt combined-cycle plant under construction at the Roxboro Steam Station, with an official Class 3 total project cost of $2,126,685,663 including financing costs, targeted for commercial operation in the fourth quarter of 2028.
Show on the map: Person County CC1
- InvestmentDuke Energy's January 30, 2026 direct testimony in Public Service Commission of South Carolina Docket 2026-30-E states that DEP's current Association for the Advancement of Cost Estimating Class 3 cost estimate for Person County CC1, including financing costs (AFUDC/CWIP), is $2,126,685,663, the figure rounded to $2.127 billion on the map. The same testimony says that total is representative of total project costs, including the North Carolina Electric Membership Corporation allocated portion. Line items that would isolate construction cost excluding AFUDC are confidential in that public filing. The testimony also gives an AACE Class 3 predictability range of approximately -10 percent ($1.9 billion) to +25 percent ($2.6 billion), which is not used to replace the official point estimate on the map.Duke Energy (filed with the Public Service Commission of South Carolina), Jan 30, 2026
- Scope and certificateThe same testimony describes CC1 as a 1,365 megawatt advanced-class combined-cycle facility with onsite ultra-low sulfur diesel backup, using GE Vernova HA.03 combustion turbines, under construction on property Duke Energy Progress owns at the existing Roxboro Steam Station in Person County. The plant is hydrogen-capable. The testimony cites the North Carolina Utilities Commission's December 6, 2024 order in Docket Nos. E-2, Sub 1318 and EC-67, Sub 55 granting a certificate of public convenience and necessity authorizing construction and operation of CC1. DEP has executed a Purchase, Construction, and Ownership Agreement with NCEMC for CC1; NCEMC is expected to own approximately 16.5 percent. This pin is not combined with the separately certificated Person County CC2 plant.Duke Energy (filed with the Public Service Commission of South Carolina), Jan 30, 2026
- Schedule and constructionThe testimony says on-site construction activity began in late third quarter 2025 for the CC1 power block, starting with civil construction and erosion and sediment control work. The official milestone table lists substantial completion and commercial operation in the fourth quarter of 2028 and final completion in the first quarter of 2029. Duke Energy Progress selected the Zachry Group as the engineering, procurement, and construction contractor for the Person County plants.Duke Energy (filed with the Public Service Commission of South Carolina), Jan 30, 2026
Next gate
Substantial completion and commercial operation targeted
Fourth quarter of 2028, according to the January 30, 2026 testimony
Official testimony targets substantial completion and commercial operation of Person County CC1 in the fourth quarter of 2028, with final completion in the first quarter of 2029. On-site construction began in late third quarter 2025.
Every step so far, and what comes next
-
DoneDecember 6, 2024
North Carolina certificate granted for CC1
The January 30, 2026 testimony cites the North Carolina Utilities Commission's December 6, 2024 order granting a certificate of public convenience and necessity authorizing construction and operation of Person County CC1.
Source: Duke Energy (filed with the Public Service Commission of South Carolina), Jan 30, 2026
-
DoneLate third quarter of 2025
On-site construction begins on the CC1 power block
Official testimony says on-site construction activity began in late third quarter 2025 for the CC1 power block, starting with civil construction and erosion and sediment control work.
Source: Duke Energy (filed with the Public Service Commission of South Carolina), Jan 30, 2026
-
DoneJanuary 30, 2026
Official Class 3 cost and schedule filed
Duke Energy filed testimony stating a $2,126,685,663 Class 3 total for CC1, including financing costs, and targeting commercial operation in the fourth quarter of 2028.
Source: Duke Energy (filed with the Public Service Commission of South Carolina), Jan 30, 2026
-
NextFourth quarter of 2028
Substantial completion and commercial operation
The same testimony targets substantial completion and commercial operation of CC1 in the fourth quarter of 2028, with final completion in the first quarter of 2029.
Source: Duke Energy (filed with the Public Service Commission of South Carolina), Jan 30, 2026
Worth knowing
- The map figure is the official Class 3 total of $2,126,685,663 including financing costs (AFUDC/CWIP), labeled $2.127 billion. The AACE predictability range of about $1.9 billion to $2.6 billion is not used to replace that point estimate, and construction-cost line items excluding AFUDC remain confidential in the public filing.
- NCEMC is expected to own approximately 16.5 percent of CC1 under an executed Purchase, Construction, and Ownership Agreement. Proposed project costs were represented as 100 percent DEP costs while recognizing that expected share, and the NCEMC portion is not used in place of the official total-project figure.
- Person County CC2 is a separately certificated sister facility with its own official cost and a later fourth-quarter 2029 commercial-operation target. The two plants are not combined on the map. Hydrogen capability and diesel backup are part of the described facility and are not added as separate costs.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.
Tracking saves to this device only. No account, no email, free.