Person County CC2
A 1,365 megawatt combined-cycle sister plant under construction next to Person County CC1, with an official Class 3 total project cost of $2.176 billion including financing costs, targeted for commercial operation in the fourth quarter of 2029.
Show on the map: Person County CC2
- InvestmentDuke Energy's January 30, 2026 direct testimony in Public Service Commission of South Carolina Docket 2026-30-E states that DEP's current Association for the Advancement of Cost Estimating Class 3 cost estimate for Person County CC2, including financing costs (AFUDC/CWIP), is $2,176,000,000, the figure used on the map. The same testimony says that total is representative of total project costs, including the North Carolina Electric Membership Corporation allocated portion. Line items that would isolate construction cost excluding AFUDC are confidential in that public filing. The testimony also gives an AACE Class 3 predictability range of approximately -10 percent ($2.0 billion) to +25 percent ($2.7 billion), which is not used to replace the official point estimate on the map.Duke Energy (filed with the Public Service Commission of South Carolina), Jan 30, 2026
- Scope and certificateThe same testimony describes CC2 as a 1,365 megawatt advanced-class combined-cycle facility with onsite ultra-low sulfur diesel backup, using GE Vernova HA.03 combustion turbines, to be built on property Duke Energy Progress owns at the existing Roxboro Steam Station in Person County, as an adjacent sister facility to Person County CC1. The plants are hydrogen-capable. The testimony cites the North Carolina Utilities Commission's October 16, 2025 order in Docket Nos. E-2 Sub 1349 and EC-67, Sub 57 granting a certificate of public convenience and necessity authorizing construction and operation of CC2. This pin is not combined with the separately certificated Person County CC1 plant or with the Marshall CTs covered in the same South Carolina filing.Duke Energy (filed with the Public Service Commission of South Carolina), Jan 30, 2026
- Schedule and constructionThe testimony includes a milestone table showing CC2 site construction was targeted to begin in the fourth quarter of 2026, with substantial completion and commercial operation in the fourth quarter of 2029 and final completion in the second quarter of 2030. It says on-site construction for the CC1 power block began in late third quarter 2025 and that work, then focused on the CC1 area, would continuously flow into the CC2 area as the contractor progressed throughout 2026. Duke Energy Progress selected the Zachry Group as the engineering, procurement, and construction contractor for both Person County plants. This pass, in late November 2026, did not find a later official report confirming that CC2 site construction had begun.Duke Energy (filed with the Public Service Commission of South Carolina), Jan 30, 2026
Next gate
Substantial completion and commercial operation targeted
Fourth quarter of 2029, according to the January 30, 2026 testimony
Official testimony targets substantial completion and commercial operation of Person County CC2 in the fourth quarter of 2029. The same filing targeted the start of CC2 site construction in the fourth quarter of 2026. This pass did not find a later official commencement confirmation.
Every step so far, and what comes next
-
DoneOctober 16, 2025
North Carolina certificate granted for CC2
The January 30, 2026 testimony cites the North Carolina Utilities Commission's October 16, 2025 order granting a certificate of public convenience and necessity authorizing construction and operation of Person County CC2.
Source: Duke Energy (filed with the Public Service Commission of South Carolina), Jan 30, 2026
-
DoneJanuary 30, 2026
Official Class 3 cost and schedule filed
Duke Energy filed testimony stating a $2,176,000,000 Class 3 total for CC2, including financing costs, and targeting site construction in the fourth quarter of 2026 and commercial operation in the fourth quarter of 2029.
Source: Duke Energy (filed with the Public Service Commission of South Carolina), Jan 30, 2026
-
NextFourth quarter of 2029
Substantial completion and commercial operation
The same testimony targets substantial completion and commercial operation of CC2 in the fourth quarter of 2029, with final completion in the second quarter of 2030.
Source: Duke Energy (filed with the Public Service Commission of South Carolina), Jan 30, 2026
Worth knowing
- The map figure is the official Class 3 total of $2,176,000,000 including financing costs (AFUDC/CWIP). The AACE predictability range of about $2.0 billion to $2.7 billion is not used to replace that point estimate, and construction-cost line items excluding AFUDC remain confidential in the public filing.
- The testimony says negotiations on NCEMC's joint ownership of CC2 were ongoing and targeted for finalization in the first quarter of 2026, with NCEMC expected to own approximately 16.5 percent. Proposed project costs were represented as 100 percent DEP costs while recognizing that expected share. This pass did not treat a later ownership close as confirmed, and NCEMC's share is not used in place of the official total-project figure.
- Person County CC1 is a separately certificated sister facility with its own official cost and an earlier fourth-quarter 2028 commercial-operation target. The two plants are not combined on the map. Hydrogen capability and diesel backup are part of the described facility and are not added as separate costs.
- The January 30, 2026 testimony listed CC2 site construction as beginning in the fourth quarter of 2026. This pass did not find a later official confirmation of that start. The map pin remains listed as under construction, and this page does not change any map stage field.