Pikka Phase 1 oil field
A $2.6 billion gross Phase 1 oil development on Alaska's North Slope that reached first oil on May 18, 2026, and is now operating while ramping toward an 80,000 barrel per day plateau.
Show on the map: Pikka Phase 1 oil field
- InvestmentSantos's August 17, 2022 final investment decision put gross capital expenditure to nameplate capacity at $2.6 billion in 2022 real terms, the figure used on the map. Santos holds a 51 percent interest, or $1.3 billion of that gross figure, and Repsol holds the remaining 49 percentSantos, Aug 17, 2022
- First oil and continuous productionOn May 18, 2026, Santos announced first oil, with flow established through the Lease Automated Custody Transfer meter into the Pikka sales oil line. On June 23, 2026, Santos said continuous production operations had begun, with the first production wells delivering about 20,000 barrels per day grossSantos, May 18, 2026
- Ramp-up, as of the third quarter of 2026Santos's October 22, 2026 third-quarter report said Pikka briefly reached its minimum expected plateau rate before the end of the third quarter, with instantaneous rates above 80,000 barrels per day gross, and that production was 69,000 barrels per day gross at the end of the quarter after two temporary curtailments. The company said production was then planned to be held at around 70,000 barrels per day for a short period to allow water injection to replenish reservoir voidage, before ramping up to 80,000 barrels per day gross. The first oil cargo was lifted in August, and 32 development wells had been drilled to dateSantos, Oct 22, 2026
Next gate
Ramp toward a sustained 80,000 barrel per day plateau
After a planned short curtailment described in the October 22, 2026 report
Santos's third-quarter report said production would be held around 70,000 barrels per day for a short period for reservoir management, then ramped up to 80,000 barrels per day gross. That is not treated here as a confirmed, already-sustained plateau.
Every step so far, and what comes next
-
DoneAugust 17, 2022
Final investment decision at $2.6 billion gross
Santos, as operator, announced FID on the $2.6 billion gross Pikka Phase 1 project, with first oil then anticipated in 2026.
Source: Santos, Aug 17, 2022
-
DoneMay 18, 2026
First oil
Santos announced first oil, with flow established through the LACT meter into the Pikka sales oil line.
Source: Santos, May 18, 2026
-
DoneJune 23, 2026
Continuous production began
Santos said continuous production operations had begun at about 20,000 barrels per day gross.
Source: Santos, Jun 23, 2026
-
NextAs of the October 22, 2026 third-quarter report
Ramp toward a sustained 80,000 barrel per day plateau
Santos said production would be held around 70,000 barrels per day for a short period, then ramped up to 80,000 barrels per day gross.
Source: Santos, Oct 22, 2026
Worth knowing
- The $2.6 billion figure is the gross Phase 1 cost at the 2022 final investment decision, in 2022 real terms. The $1.3 billion Santos-share figure is 51 percent of that gross cost, not an added budget.
- Nameplate capacity of 80,000 barrels per day gross was the original design target. Official third-quarter 2026 materials say instantaneous rates briefly exceeded that level, but they do not treat a sustained plateau as already achieved.
- Later Pikka Unit resources such as Quokka and Horseshoe are separate from this Phase 1 pin and are not included in the $2.6 billion figure.
- The map pin is approximate, west of the Colville River.
Last checked Nov 23, 2026. We add a step when it happens and link the source.