Track your favorite projects · LNG export
Port Arthur LNG Phase 1
The first two liquefaction trains at Port Arthur, under construction since 2023 and heading toward first commercial operations in 2027.
Show on the map: Port Arthur LNG Phase 1
- CostAbout $13 billionPort Arthur LNG, Nov 23, 2026
- CapacityAbout 13 million tonnes a year from two trains, plus two LNG storage tanksPort Arthur LNG, Nov 23, 2026
- CustomersFully subscribed under long-term contracts with ConocoPhillips, RWE, PKN Orlen, INEOS and EngiePort Arthur LNG, Nov 23, 2026
- ScheduleCommercial operations expected at or near the end of 2027 for Train 1, and in 2028 for Train 2Port Arthur LNG, Nov 23, 2026
Next gate
Train 1 in commercial operation
At or near the end of 2027
The project's published target for Train 1. Train 2 is targeted for 2028.
Every step so far, and what comes next
-
Done2023
Construction began
The project page says construction began in 2023.
Source: Port Arthur LNG, Nov 23, 2026
-
DoneMarch 20, 2023
Final investment decision
Sempra reached FID, closed the ConocoPhillips joint venture and $6.8 billion of project debt, and issued Bechtel a final notice to proceed.
Source: Sempra, Mar 20, 2023
-
DonePast 12 months through Oct 2026
Major equipment in place
Sempra said Train 1 and Train 2 main cryogenic heat exchangers were installed, both storage tanks reached raised-roof milestones, the powerhouse and control room were energized, and the heavy-lift program was finished.
-
NextAt or near the end of 2027
Train 1 in commercial operation
The project's published target.
Source: Port Arthur LNG, Nov 23, 2026
-
Expected2028
Train 2 in commercial operation
The project's published target.
Source: Port Arthur LNG, Nov 23, 2026
Worth knowing
- Dates are company targets.
- Sempra's 2023 launch release also put Phase 1 capital spending at $13 billion.
Go deeper
Last checked Nov 23, 2026. We add a step when it happens and link the source.
Tracking saves to this device only. No account, no email, free.