Port Arthur LNG Phase 1

Sempra Infrastructure and ConocoPhillips · Port Arthur, Jefferson County, Texas

Under construction

The first two liquefaction trains at Port Arthur, under construction since 2023 and heading toward first commercial operations in 2027.

Show on the map: Port Arthur LNG Phase 1

Next gate

Train 1 in commercial operation

At or near the end of 2027

The project's published target for Train 1. Train 2 is targeted for 2028.

Every step so far, and what comes next

  1. Done2023

    Construction began

    The project page says construction began in 2023.

  2. DoneMarch 20, 2023

    Final investment decision

    Sempra reached FID, closed the ConocoPhillips joint venture and $6.8 billion of project debt, and issued Bechtel a final notice to proceed.

  3. DonePast 12 months through Oct 2026

    Major equipment in place

    Sempra said Train 1 and Train 2 main cryogenic heat exchangers were installed, both storage tanks reached raised-roof milestones, the powerhouse and control room were energized, and the heavy-lift program was finished.

  4. NextAt or near the end of 2027

    Train 1 in commercial operation

    The project's published target.

  5. Expected2028

    Train 2 in commercial operation

    The project's published target.

Worth knowing

Go deeper

Last checked Nov 23, 2026. We add a step when it happens and link the source.