PowerOn Midwest 765 kV transmission line, South Dakota segment
An official September 2026 South Dakota facility-permit application estimates the PowerOn Midwest South Dakota project at $1.3 billion to $1.7 billion in 2024 dollars, with service expected in 2034. The docket remains pending.
Show on the map: PowerOn Midwest 765 kV transmission line, South Dakota segment
- Official cost range for the South Dakota projectThe official September 2026 facility-permit application by Northern States Power Company, doing business as Xcel Energy, and Otter Tail Power Company states that all project facilities, including substations, are expected to be in service in 2034 and are estimated to cost $1.3 billion in 2024 dollars as a base cost to $1.7 billion in 2024 dollars as a base-plus-contingency cost. Section 8 of the same official application gives the more precise range of approximately $1.284 billion in 2024 dollars (base) to $1.666 billion in 2024 dollars (high range, base plus a 30 percent contingency). The official $1.3 billion low-end figure, which matches the rounded base estimate used on the map, is the figure used on the map. The map label is $1.3B+. The official application presents these estimates for the South Dakota project described in the filing, from Big Stone South to the South Dakota/Minnesota border. Official Minnesota segments of PowerOn Midwest are described separately and are not included in these cost estimates.Northern States Power Company, doing business as Xcel Energy, and Otter Tail Power Company, Sep 1, 2026
- Scope and pending permitThe official application describes an approximately 90-mile 765 kilovolt transmission line in Grant, Deuel, and Brookings counties; expansions of the Big Stone South Substation and the Brookings County Substation, including a 765 kilovolt expansion area about five miles from the existing Brookings County Substation; and an approximately five-mile 345 kilovolt line connecting those Brookings County expansions. The official South Dakota Public Utilities Commission notice states that the Commission received the application on September 4, 2026, and that the applicants estimate the total construction cost at approximately $1.3 billion to $1.7 billion, with service in 2034. The official docket page lists the case as pending.South Dakota Public Utilities Commission, Sep 9, 2026
Next gate
Official docket remains pending after the September 4, 2026 application filing
After the official September 4, 2026 application filing
The official SDPUC notice states that the Commission received the facility-permit application on September 4, 2026, and that the applicants anticipate the project to be in service in 2034. The official docket page lists the matter as pending. This pass did not find an official construction-start date in the application or notice. The map pin remains listed as announced.
Every step so far, and what comes next
-
DoneSeptember 4, 2026
Xcel Energy and Otter Tail Power file a South Dakota facility-permit application
The official SDPUC notice states that the Commission received the application on September 4, 2026, for the PowerOn Midwest South Dakota project, with an official estimated construction cost of approximately $1.3 billion to $1.7 billion, the low end of which is the figure used on the map, and service expected in 2034.
Source: South Dakota Public Utilities Commission, Sep 9, 2026
-
NextAfter the official September 4, 2026 application filing
Official docket remains pending after the September 4, 2026 application filing
The official SDPUC notice states that the Commission received the facility-permit application on September 4, 2026, and that the applicants anticipate the project to be in service in 2034. The official docket page lists the matter as pending. This pass did not find an official construction-start date in the application or notice. The map pin remains listed as announced.
Source: South Dakota Public Utilities Commission, Sep 9, 2026
Worth knowing
- The map figure is the official rounded low end of the applicants' $1.3 billion to $1.7 billion estimate, in 2024 dollars, for the South Dakota project only. The same official application states a more precise base of approximately $1.284 billion and a high range of $1.666 billion in 2024 dollars, including a 30 percent contingency. This page does not change any map usd field.
- Official Minnesota segments of PowerOn Midwest are described separately in the application and are not included in the official South Dakota cost estimates used here.
- The official application notes that the Big Stone South Substation Expansion estimate reflects MISO's Appendix A cost estimate, and that Otter Tail was preparing an updated estimate. The official docket remains pending. The map pin remains listed as announced, and this page does not change any map stage field. The map location is approximate, in Deuel County along the planned route.
Go deeper
Last checked Nov 24, 2026. We add a step when it happens and link the source.