Qcells solar expansion, Cartersville and Dalton
A more than $2.5 billion solar manufacturing expansion, counted as $2.5 billion on the map, with official cell production at the Cartersville plant beginning June 9, 2026.
Show on the map: Qcells solar expansion, Cartersville and Dalton
- InvestmentGovernor Brian Kemp's January 11, 2023 official release said Qcells will invest more than $2.5 billion to expand solar module manufacturing in Georgia, building a new facility in Cartersville and adding a third facility at its Dalton location. The map counts $2.5 billionOffice of the Governor of Georgia, Jan 11, 2023
- ScopeThe 2023 state release said the new Cartersville plant at Highland 75 Corporate / Industrial Park would manufacture 3.3 gigawatts of solar ingots, wafers, cells, and finished panels and create about 2,000 jobs, and that a new Dalton facility would add 2 gigawatts and 510 jobs. Qcells's June 9, 2026 official announcement said the Cartersville facility will add 3.3 gigawatts of vertically integrated ingot, wafer, and cell capacity and 3.5 gigawatts of module capacity when fully operational, and that the expanded Dalton factory tripled module capacity to 5.1 gigawatts in late 2023Qcells North America, Jun 9, 2026
- Production statusOn June 9, 2026, Qcells announced it had begun manufacturing solar cells at Cartersville and that Cartersville module assembly was then at full capacity, building 16,700 panels a day. The company said it expected to be at full production by the third quarter of 2026, with total Georgia module capacity reaching 8.6 gigawatts a year, and that its Georgia operations were expected to employ nearly 4,000 people. This pass did not find a later official announcement confirming that the full ingot, wafer, and cell ramp had been completedQcells North America, Jun 9, 2026
Next gate
Full Cartersville ingot, wafer, and cell ramp, if completed as planned
Expected by the third quarter of 2026 in the June 9, 2026 announcement; later official confirmation not found this pass
Qcells's June 9, 2026 announcement said the company expected full production by the third quarter of 2026. This pass did not find a later official confirmation that those remaining lines had reached full capacity, so that milestone is not marked complete.
Every step so far, and what comes next
-
DoneJanuary 11, 2023
Georgia announced a more than $2.5 billion expansion
Governor Kemp said Qcells would build a new Cartersville plant and add a Dalton facility, creating more than 2,500 new jobs.
-
DoneJune 9, 2026
Cell production began at Cartersville
Qcells announced it had begun manufacturing solar cells at Cartersville and that module assembly there was at full capacity.
-
NextThird quarter of 2026, as expected in the June announcement
Full production expected; later official confirmation not found
The June 9, 2026 official announcement expected full production by the third quarter of 2026. This pass did not find a later official confirmation that the remaining lines had reached that capacity.
Worth knowing
- The official 2023 state figure is more than $2.5 billion. The map counts $2.5 billion and is left unchanged.
- The pin is at Cartersville. The investment also covers the Dalton expansion.
- Capacity figures changed slightly between the 2023 announcement, which projected 8.4 gigawatts of Georgia panel production by 2024, and the June 2026 company announcement, which described 8.6 gigawatts of module capacity. Both official figures are recorded rather than collapsed into one number.
- The June 9, 2026 expectation of full production by the third quarter of 2026 is not treated as a confirmed later milestone without a subsequent official confirmation.