Track your favorite projects · Data centers

QTS Eagle Mountain data center campus

QTS Data Centers · Utah County, Utah

Under construction

A five-building, 193-acre data center campus beside the Meta site in Eagle Mountain, with more than 2,000 construction jobs.

Show on the map: QTS Eagle Mountain

Next gate

Buildings 1 to 3 complete

End of 2026 (company)

QTS expects buildings 1, 2 and 3 to be complete by the end of 2026.

Every step so far, and what comes next

  1. DoneApril 17, 2026

    Third building topped out

    Layton and QTS topped out the third building; work began in September 2025.

  2. NextEnd of 2026 (company)

    Buildings 1 to 3 complete

    QTS expects buildings 1, 2 and 3 to be complete by the end of 2026.

Worth knowing

Last checked Nov 28, 2026. We add a step when it happens and link the source.

Tracking saves to this device only. No account, no email, free.