Red Oak Ridge Energy Center
A permitted 1,125 megawatt nameplate simple-cycle natural gas plant in Kenosha County, with an official construction-and-acquisition cost of $1,769,801,000, after a certificate with conditions was granted on October 15, 2026.
Show on the map: Red Oak Ridge Energy Center
- InvestmentWisconsin Electric Power Company's November 20, 2025 official application in Public Service Commission Docket 6630-BS-104 proposes to acquire and construct the Red Oak Ridge Energy Center at a total cost of approximately $1.770 billion, or $1,573 per kilowatt. A capital-cost table in the same application totals $1,769,801,000, the figure rounded to $1.77 billion on the map. The official application says that price includes turbines, electrical systems, interconnection, and owner costs, and excludes Affected System costs that may be assessed later by regional transmission operators.Wisconsin Electric Power Company, Nov 20, 2025
- Scope and certificateThe same official application describes a natural gas-fueled 1,125 megawatt nameplate simple-cycle combustion turbine plant in Kenosha County, to be built by Invenergy and acquired by Wisconsin Electric, including transfer of certificate rights from Docket 9837-CE-100. The Public Service Commission of Wisconsin's October 15, 2026 official statement said the Commission granted a certificate of public convenience and necessity with conditions for the Red Oak Ridge Energy Center Project. That statement does not restate a dollar figure. It also granted a certificate the same day for the separate Foundry Ridge Energy Center Project, which is not included in this pin.Public Service Commission of Wisconsin, Oct 15, 2026
- ScheduleThe November 20, 2025 official application said construction of Red Oak Ridge was scheduled to begin in October 2026 and was expected to achieve a partial in-service date by December 31, 2029, and full commercial operation by June 30, 2030. This pass, in late November 2026, did not find a later official report confirming that construction had begun. The map pin remains listed as permitted.Wisconsin Electric Power Company, Nov 20, 2025
Next gate
Partial in-service targeted, if construction proceeds on the application schedule
Partial in-service by December 31, 2029, and full commercial operation by June 30, 2030, according to the November 20, 2025 official application
The official application scheduled construction to begin in October 2026, with a partial in-service date by December 31, 2029, and full commercial operation by June 30, 2030. A certificate with conditions was granted on October 15, 2026. This pass did not find a later official commencement confirmation. The map pin remains listed as permitted.
Every step so far, and what comes next
-
DoneNovember 20, 2025
Wisconsin Electric files the official $1,769,801,000 cost
The company applied to acquire and construct the 1,125 megawatt nameplate plant at a total cost of $1,769,801,000, the figure used on the map, and scheduled a partial in-service date by December 31, 2029.
-
DoneOctober 15, 2026
Commission grants a certificate with conditions
The Public Service Commission of Wisconsin granted a certificate of public convenience and necessity with conditions for Red Oak Ridge. The official statement does not restate a dollar figure. Foundry Ridge, approved the same day, is a separate project.
Source: Public Service Commission of Wisconsin, Oct 15, 2026
-
NextDecember 31, 2029, for partial in-service, according to the official application
Partial in-service targeted
The official application expects a partial in-service date by December 31, 2029, and full commercial operation by June 30, 2030. This pass did not find a later official construction-start confirmation.
Worth knowing
- The map figure is the official $1,769,801,000 total in the November 20, 2025 application, labeled $1.77 billion. Affected System costs that may be assessed later are excluded from that official total and are not added here.
- The October 15, 2026 Commission statement grants a certificate with conditions and does not restate a dollar figure. Later public descriptions of plant capacity as up to 1,186 or 1,210 megawatts differ from the official 1,125 megawatt nameplate used in the acquisition application and on this page.
- Foundry Ridge is a separate plant approved the same day and is not included in this pin.
- The November 20, 2025 application scheduled construction to begin in October 2026. This pass did not find a later official confirmation that construction had started. The map pin remains listed as permitted, and this page does not change any map stage field.
Go deeper
Last checked Nov 24, 2026. We add a step when it happens and link the source.