Redwood Materials battery materials campus, McCarran
An official October 1, 2026 Nevada GOED annual report treats Redwood Materials as a qualified $1.1 billion investment project, reports about $1.008 billion in capital investment through June 30, 2026, and finds satisfactory progress toward the required $1 billion minimum.
Show on the map: Redwood Materials battery materials campus, McCarran
- Official planned investment used for the incentiveThe official October 1, 2026 Nevada Governor's Office of Economic Development annual report under NRS 360.895 covers the qualified project commonly known as Redwood Materials, Inc., approved by the GOED Board on December 2, 2022. The official report says that over the 15-year life of the incentive agreement, GOED estimated abatements would total $80.7 million based on an investment of $1.1 billion. The official $1.1 billion planned investment used for that estimate is the amount used on the map.Nevada Governor's Office of Economic Development, Oct 1, 2026
- Official investment reported through June 30, 2026, and progress findingThe same official report says the agreement includes 100 percent claw-back plus interest provisions if the project fails to reach the required minimum 10-year investment of $1 billion. It says Redwood Materials reports an estimated total investment of $1 billion through June 30, 2026, and a table in the report lists total capital investment of $1,007,580,542. Based on that investment, and observations of physical progress at the site, GOED determined for fiscal year 2026 that Redwood Materials is making satisfactory progress towards meeting the investment requirements necessary to maintain its status as a qualified project.Nevada Governor's Office of Economic Development, Oct 1, 2026
Next gate
Official October 1, 2026 GOED report found satisfactory progress and about $1.008 billion invested through June 30, 2026
After the official fiscal year 2026 annual report
The official GOED report used a $1.1 billion planned investment to estimate incentive abatements, reported $1,007,580,542 in total capital investment through June 30, 2026, and found satisfactory progress toward the required $1 billion minimum. The map pin remains listed as operating.
Every step so far, and what comes next
-
DoneDecember 2, 2022
GOED Board approves Redwood Materials as a qualified project
The official October 1, 2026 annual report says Redwood Materials, Inc., was approved by the GOED Board on December 2, 2022.
Source: Nevada Governor's Office of Economic Development, Oct 1, 2026
-
DoneOctober 1, 2026
GOED reports about $1.008 billion invested and satisfactory progress
The official fiscal year 2026 annual report used a $1.1 billion planned investment for its incentive estimate, listed $1,007,580,542 in total capital investment through June 30, 2026, and found satisfactory progress toward the required $1 billion minimum.
Source: Nevada Governor's Office of Economic Development, Oct 1, 2026
-
NextAfter the official fiscal year 2026 annual report
Official October 1, 2026 GOED report found satisfactory progress and about $1.008 billion invested through June 30, 2026
The official GOED report used a $1.1 billion planned investment to estimate incentive abatements, reported $1,007,580,542 in total capital investment through June 30, 2026, and found satisfactory progress toward the required $1 billion minimum. The map pin remains listed as operating.
Source: Nevada Governor's Office of Economic Development, Oct 1, 2026
Worth knowing
- The map figure is the official $1.1 billion planned investment GOED used for the incentive estimate in the October 1, 2026 annual report. The same official report states a required minimum 10-year investment of $1 billion and reports $1,007,580,542 in capital investment through June 30, 2026. Those official amounts are not used to replace the $1.1 billion map figure, and this page does not change any map usd, stage, or pledge field.
- Official transferable tax credits and tax abatements in the same report are incentives and are not added to the map figure.
- The official report identifies the project with Storey County assessor records. It does not restate a more specific campus address in the text extracted this pass. The map pin remains labeled McCarran.