Track your favorite projects · Offshore wind
Revolution Wind offshore wind farm
A 704 megawatt offshore wind farm that reached 100% operational status on November 5, 2026, with 400 megawatts contracted to Rhode Island and 304 to Connecticut.
Show on the map: Revolution Wind offshore wind farm
- Investment$5 billion, the figure used on the map. Official Rhode Island statements marking full operation on November 5, 2026, did not publish a final project costRevolution Wind, LLC, filed in the U.S. District Court for the District of Columbia, Sep 4, 2025
- CapacityRhode Island contracted for 400 megawatts and Connecticut for the remaining 304 megawatts, for a total of 704 megawatts. The state energy office said the project is expected to generate enough electricity to power about 350,000 homesRhode Island Office of Energy Resources, Nov 5, 2026
- LocationAbout 15 miles south of Rhode Island in federal watersRhode Island Office of Energy Resources, Nov 5, 2026
- CompletionOn November 5, 2026, Governor Dan McKee and the Rhode Island Office of Energy Resources said Revolution Wind had achieved 100% operational statusOffice of the Governor of Rhode Island, Nov 5, 2026
Next gate
Commercial operation continues
In service since November 5, 2026
Official Rhode Island statements on November 5, 2026, said the project had reached 100% operational status. No further construction is described there.
Every step so far, and what comes next
-
Done2018
Rhode Island and Connecticut selected the project
The Rhode Island Office of Energy Resources said the two states selected Revolution Wind in 2018.
Source: Rhode Island Office of Energy Resources, Nov 5, 2026
-
DoneNovember 5, 2026
Project reached 100% operational status
Governor McKee and the state energy office said Revolution Wind had achieved full operation.
-
NextIn service since November 5, 2026
Commercial operation continues
Official state statements describe a completed, fully operational project.
Worth knowing
- The map counts $5 billion, matching the amount the project company said it had spent or committed as of its September 4, 2025 court complaint. That is not a published final total cost, and official Rhode Island completion statements reviewed for this pass did not give a later figure.
- The map pin is onshore at the interconnection in North Kingstown. The turbines are about 15 miles offshore.
- Estimated bill savings and wholesale-price effects cited by the Office of Energy Resources are state estimates over the 20-year power purchase agreement, not an independent audit.
Last checked Nov 23, 2026. We add a step when it happens and link the source.