Rhyolite Ridge lithium-boron project
A permitted lithium and boron mine and processing plant that would be the first U.S. project to produce both onsite.
Show on the map: Rhyolite Ridge
- Still neededAbout $1.7 billion to build, per Ioneer's June 2025 estimateIoneer, Dec 2025
- Federal loan$996 million from the Department of Energy, closed January 2025, not drawable until a partner is foundIoneer, Dec 2025
- Spent so farMore than $200 million, per IoneerIoneer, Dec 2025
Next gate
Ioneer brings in a financial partner
No date published
Ioneer must raise and spend about $700 million in partner equity before it can draw the Department of Energy loan. No date is published.
Every step so far, and what comes next
-
DoneJan 2025
Department of Energy closes a $996 million loan
The U.S. Department of Energy closed a $996 million loan, which Ioneer cannot draw until it brings in a financial partner.
Source: Ioneer, Dec 2025
-
DoneDec 2025
Ioneer publishes its project fact sheet
The fact sheet says the project is permitted and still needs about $1.7 billion to build the mine, chemical plant and sulfuric acid plant.
Source: Ioneer, Dec 2025
-
NextNo date published
Ioneer brings in a financial partner
Ioneer must raise and spend about $700 million in partner equity before it can draw the Department of Energy loan. No date is published.
Source: Ioneer, Dec 2025
Worth knowing
- Construction has not started. The figure is the additional money needed, not the amount spent.
Last checked Nov 28, 2026. We add a step when it happens and link the source.