Rio Grande LNG Train 4
A fourth liquefaction train of about 6 million tonnes a year at NextDecade's Port of Brownsville export plant, under construction by Bechtel.
Show on the map: Rio Grande LNG Train 4
- InvestmentAbout $6.7 billion for Train 4 and related infrastructure, including EPC costs, owner's costs, contingencies, financing fees, interest during construction, other costs, and estimated true-up payments for shared facilitiesNextDecade, Sep 9, 2025
- CapacityAbout 6 million tonnes a year. After the Train 4 FID, NextDecade said about 24 million tonnes a year was under construction at the siteNextDecade, Sep 9, 2025
- ContractsCommercially supported by 4.6 million tonnes a year of 20-year sale and purchase agreements with ADNOC, TotalEnergies, and AramcoNextDecade, Sep 9, 2025
- FinancingAbout $6.7 billion in committed financing at financial close: a $3.85 billion term loan at Rio Grande LNG Train 4, LLC, $1.13 billion of NextDecade equity, and $1.70 billion of equity from Global Infrastructure Partners (a part of BlackRock), GIC, Mubadala, and TotalEnergies. NextDecade's initial economic interest is 40%, rising to 60% after the financial investors hit certain returnsNextDecade, Sep 9, 2025
- ProgressAs of September 2026, Train 4 was 22.5% complete overall (engineering 82.9%, procurement 39.2%, construction 2.8%)NextDecade, Oct 29, 2026
Next gate
Guaranteed substantial completion and first commercial delivery
Second half of 2030
The September 9, 2025 FID release said the guaranteed substantial completion date, and the date of first commercial delivery under the Train 4 sale and purchase agreements, is anticipated in the second half of 2030.
Every step so far, and what comes next
-
DoneSeptember 9, 2025
Final investment decision and notice to proceed
NextDecade took a positive FID, closed financing to fully fund Train 4, and issued full notice to proceed to Bechtel under a lump-sum, turnkey EPC contract.
Source: NextDecade, Sep 9, 2025
-
DoneSeptember 2026
Train 4 at 22.5% complete
NextDecade's third-quarter 2026 update reported overall completion of 22.5%, with construction at 2.8%.
Source: NextDecade, Oct 29, 2026
-
NextSecond half of 2030
Guaranteed substantial completion and first commercial delivery
The date given in the FID release for guaranteed substantial completion and first commercial delivery under the Train 4 contracts.
Source: NextDecade, Sep 9, 2025
Worth knowing
- The $6.7 billion figure includes financing fees and interest during construction, not only construction costs, and includes estimates of true-up payments to trains already in service for a share of common facilities.
- This tracker covers Train 4 only. Phase 1 (Trains 1 to 3) and Train 5 have their own map pins and tracker pages.
- Completion dates are company targets under the Bechtel contract.