Rio Grande LNG Train 5

NextDecade · Port of Brownsville, Cameron County, Texas

Under construction

A fifth liquefaction train of about 6 million tonnes a year at NextDecade's Port of Brownsville export plant, under construction by Bechtel.

Show on the map: Rio Grande LNG Train 5

Next gate

Guaranteed substantial completion and first commercial delivery

First half of 2031

The October 16, 2025 FID release said the guaranteed substantial completion date, and the date of first commercial delivery under the Train 5 sale and purchase agreements, is anticipated in the first half of 2031.

Every step so far, and what comes next

  1. DoneOctober 16, 2025

    Final investment decision and notice to proceed

    NextDecade took a positive FID, closed financing to fully fund Train 5, and issued full notice to proceed to Bechtel under a lump-sum, turnkey EPC contract.

  2. DoneSeptember 2026

    Train 5 at 14.0% complete

    NextDecade's third-quarter 2026 update reported overall completion of 14.0%, with construction at 0.5%.

  3. NextFirst half of 2031

    Guaranteed substantial completion and first commercial delivery

    The date given in the FID release for guaranteed substantial completion and first commercial delivery under the Train 5 contracts.

Worth knowing

Go deeper

Last checked Nov 23, 2026. We add a step when it happens and link the source.