Rivian Georgia plant

Rivian · Stanton Springs North, outside Social Circle, Morgan and Walton counties, Georgia

Under construction

A second U.S. assembly plant for Rivian's midsize electric vehicles, with a 2021 investment figure of $5 billion and customer production targeted for 2028.

Show on the map: Rivian Georgia plant

Next gate

Customer vehicle production

Anticipated in 2028

Rivian's September 16, 2025 groundbreaking release said the first phase of construction was expected to begin in 2026, with customer vehicle production in Georgia anticipated in 2028.

Every step so far, and what comes next

  1. DoneDecember 16, 2021

    Georgia plant announced

    Governor Kemp announced a $5 billion Rivian campus at Stanton Springs North, then planned to start construction in summer 2022 and production in 2024.

  2. DoneSeptember 16, 2025

    Groundbreaking ceremony

    Rivian held a groundbreaking with Governor Kemp and said construction was expected to begin in 2026, with customer production anticipated in 2028.

  3. Done2026

    Vertical construction began

    Rivian's 2025 Impact Report says that after site preparation in 2025, vertical construction began in 2026.

  4. Next2028

    Customer vehicle production

    The date given in the September 16, 2025 groundbreaking release.

Worth knowing

Last checked Nov 23, 2026. We add a step when it happens and link the source.