Sabine Pass LNG Stage V expansion

Cheniere Energy Partners · Sabine Pass LNG Terminal, Cameron Parish, Louisiana

Permitted, no final investment decision yet

Three more liquefaction trains at Cheniere's existing Sabine Pass terminal, approved by FERC and awaiting a final investment decision.

Show on the map: Sabine Pass LNG Stage V expansion

Next gate

Final investment decision on Phase 1

By early 2027

Cheniere said a positive FID on Train 7 is subject to remaining approvals and an acceptable financing plan, and expected it by early 2027.

Every step so far, and what comes next

  1. DoneJune 6, 2025

    Amended DOE application

    Sabine Pass amended its export application and estimated it would spend about $15 billion on the expansion.

  2. DoneMay 28, 2026

    EPC contract signed

    Cheniere Partners signed a lump-sum EPC contract with Bechtel for Phase 1 and issued a limited notice to proceed.

  3. DoneSept 2026

    FERC environmental statement and loan commitments

    FERC issued the final environmental impact statement. Cheniere also obtained term-loan commitments sized to about 50% of Phase 1 costs, with closing tied to a positive FID.

  4. DoneNov 19, 2026

    FERC approval

    FERC authorized three additional liquefaction trains at Sabine Pass, plus two feed-gas pipeline projects.

  5. NextBy early 2027

    Final investment decision on Phase 1

    Cheniere's stated target, still subject to remaining approvals and financing.

Worth knowing

Last checked Nov 23, 2026. We add a step when it happens and link the source.