Sabine Pass LNG Stage V expansion
Three more liquefaction trains at Cheniere's existing Sabine Pass terminal, approved by FERC and awaiting a final investment decision.
Show on the map: Sabine Pass LNG Stage V expansion
- CostAbout $15 billion, Cheniere's estimate in a June 2025 DOE filingSabine Pass Liquefaction (U.S. Department of Energy filing), Jun 6, 2025
- CapacityUp to about 20 million tonnes a year from Trains 7, 8 and 9, on top of more than 30 million tonnes already in operationCheniere Energy Partners, May 28, 2026
- Phase 1Train 7 and a boil-off gas reliquefaction unit, with expected production of more than 6 million tonnes a yearCheniere Energy Partners, May 28, 2026
- ContractorBechtel has a lump-sum EPC contract for Phase 1 and a limited notice to proceed for early engineering and procurementCheniere Energy Partners, May 28, 2026
Next gate
Final investment decision on Phase 1
By early 2027
Cheniere said a positive FID on Train 7 is subject to remaining approvals and an acceptable financing plan, and expected it by early 2027.
Every step so far, and what comes next
-
DoneJune 6, 2025
Amended DOE application
Sabine Pass amended its export application and estimated it would spend about $15 billion on the expansion.
Source: Sabine Pass Liquefaction (U.S. Department of Energy filing), Jun 6, 2025
-
DoneMay 28, 2026
EPC contract signed
Cheniere Partners signed a lump-sum EPC contract with Bechtel for Phase 1 and issued a limited notice to proceed.
-
DoneSept 2026
FERC environmental statement and loan commitments
FERC issued the final environmental impact statement. Cheniere also obtained term-loan commitments sized to about 50% of Phase 1 costs, with closing tied to a positive FID.
-
DoneNov 19, 2026
FERC approval
FERC authorized three additional liquefaction trains at Sabine Pass, plus two feed-gas pipeline projects.
-
NextBy early 2027
Final investment decision on Phase 1
Cheniere's stated target, still subject to remaining approvals and financing.
Worth knowing
- The map counts $13 billion plus, the low end of an earlier preliminary range. The later June 2025 DOE filing estimates about $15 billion.
- No final investment decision has been made, so the money is not committed.
- The June 2025 filing's 2030 first-export timing assumed an earlier FERC approval than the one issued on Nov 19, 2026.
Last checked Nov 23, 2026. We add a step when it happens and link the source.