Track your favorite projects · Semiconductors
Samsung Taylor fab
Samsung's leading-edge chip fab outside Austin, now running early 2nm wafers.
Show on the map: Samsung Taylor fab
- Original estimate$17 billion for the Taylor fab (map figure)Samsung Electronics, Nov 24, 2021
- Federal awardUp to $4.745 billion in CHIPS funding, paid as milestones are metU.S. Department of Commerce, Dec 20, 2024
- Texas planOver $37 billion across Taylor and Austin, including two leading-edge fabs and an R&D fab in TaylorU.S. Department of Commerce, Dec 20, 2024
Next gate
Volume supply
2027
Samsung plans to finish production verification by the end of 2026 and start supplying chips in earnest in 2027, per Korean trade press.
Every step so far, and what comes next
-
DoneNov 24, 2021
Taylor picked
Samsung announced Taylor as the site of its new advanced fab.
-
DoneDec 20, 2024
CHIPS award finalized
Commerce awarded up to $4.745 billion.
-
DoneApr 2026
Equipment move-in
Samsung held an equipment move-in ceremony at the fab.
Source: Businesskorea, Sep 16, 2026
-
DoneSep 2026
Prototype 2nm wafers
The fab started prototype production, including Tesla's AI5 chip, on some lines.
Source: Businesskorea, Sep 16, 2026
-
ExpectedEnd of 2026
Production verification done
Samsung's reported target.
Source: Businesskorea, Sep 16, 2026
-
Next2027
Supply in earnest
Reported start of full supply.
Source: Businesskorea, Sep 16, 2026
Worth knowing
- The map counts the original $17 billion for Taylor only; the $37 billion figure includes Austin.
- Production timing after September 2026 comes from trade press citing industry sources, not Samsung releases.
Last checked Nov 23, 2026. We add a step when it happens and link the source.