Savannah River Plutonium Processing Facility
Turning the unfinished MOX building at Savannah River into a plant making at least 50 plutonium pits a year.
Show on the map: Savannah River Plutonium Processing Facility
- Approved baseline$23.5 billion for the Main Process BuildingEngineering News-Record, Nov 9, 2026
- OutputAt least 50 plutonium pits a yearEngineering News-Record, Nov 9, 2026
- BuildingReuses the roughly 400,000 square foot shell left from the canceled MOX plantEngineering News-Record, Nov 9, 2026
- WorkforceMore than 3,000 additional workers expected at peak constructionEngineering News-Record, Nov 9, 2026
Next gate
Construction complete
December 2038
DOE set a December 2038 completion target when it approved the baseline on Oct 15, 2026.
Every step so far, and what comes next
-
Done2018
MOX canceled
DOE ended the MOX contract and chose to convert the building to pit production.
-
DoneOct 2024
Project restructured
DOE folded the work into three projects and let the main building set its baseline at 60% design.
-
DoneDec 2024
Preliminary design review
The project finished its preliminary design review.
-
DoneOct 15, 2026
Baseline and full construction approved
DOE approved the $23.5 billion baseline and authorized full construction.
-
NextDec 2038
Completion target
DOE's approved schedule.
Worth knowing
- The $23.5 billion covers the Main Process Building only, not every support project on the site.
- The cost is more than twice the top of DOE's 2021 preliminary range, and GAO has reported design and contractor problems.
- Pin is approximate, inside the Savannah River Site.
Last checked Nov 23, 2026. We add a step when it happens and link the source.