SFO Terminal 3 West Modernization
A $2.6 billion renovation and expansion of the western half of Terminal 3, under construction, with the expanded western half expected to open in fall 2027.
Show on the map: SFO Terminal 3 West Modernization
- InvestmentSFO's October 30, 2025 official update put the Terminal 3 West Modernization project at $2.6 billion, the figure used on the map. It will renovate the existing 650,000 square foot western half of Terminal 3, including a seismic retrofit, an expanded security checkpoint, and new passenger amenities, and will create 200,000 square feet of additional spaceSan Francisco International Airport, Oct 30, 2025
- ScheduleThe same official update said the renovated and expanded western half is expected to open in fall 2027, a new six-story lounge and office building is expected to open in early 2028, and a renovated check-in lobby on the eastern end of Terminal 3 is expected to open in early 2029San Francisco International Airport, Oct 30, 2025
- Later official construction actionOn November 3, 2026, the San Francisco Airport Commission approved Phase C22 of the design-build contract with Turner Construction Company, increasing the contract not-to-exceed amount by $43,377,910 to a new contract amount not to exceed $2,103,806,788, with no change to contract duration. That contract cap is not a replacement for the official $2.6 billion project costSan Francisco Airport Commission, Nov 3, 2026
Next gate
Expanded western half expected to open
Fall 2027
SFO's official October 30, 2025 update said the renovated and expanded western half is expected to open in fall 2027, with later pieces opening in early 2028 and early 2029. The November 3, 2026 commission action continued the design-build contract without changing those published opening dates.
Every step so far, and what comes next
-
DoneOctober 30, 2025
SFO published the next construction phase and the $2.6 billion cost
The official update described upcoming AirTrain, ticket-counter, and curbside changes and restated the project schedule through 2029.
-
DoneNovember 3, 2026
Airport Commission approved another design-build contract phase
The commission approved Phase C22, raising the Turner Construction contract not-to-exceed amount to about $2.10 billion, with no change to contract duration.
-
NextFall 2027
Expanded western half expected to open
SFO's official update targets fall 2027 for the renovated and expanded western half, early 2028 for the six-story building, and early 2029 for the eastern check-in lobby.
Worth knowing
- The map figure is the official $2.6 billion project cost from SFO's October 30, 2025 construction update. The November 3, 2026 design-build contract not-to-exceed amount of about $2.10 billion is a contract cap, not a new official project total, and is not used to replace the map figure.
- This pass did not find a later official SFO press release that changed the fall 2027, early 2028, or early 2029 opening dates.