Sites Reservoir, Sacramento Valley

Sites Project Authority · Glenn and Colusa counties, California, west of Maxwell

Permitted, financing being advanced

A planned off-stream reservoir of up to 1.5 million acre-feet, now fully permitted for construction once financing is in place.

Show on the map: Sites Reservoir, Sacramento Valley

Next gate

Construction start

Assumed in 2027, after financing

The governor's office said all regulatory approvals needed to start construction are in place and that the authority is now advancing financing. The Plan of Finance assumes construction begins in 2027.

Every step so far, and what comes next

  1. DoneOctober 2026

    Plan of Finance published

    The authority published a plan based on August 2026 assumptions, including an $8.1 billion 2026-dollar estimate and a 2027 to 2035 construction period.

  2. DoneNov 4, 2026

    Water right approved

    The State Water Board approved the project's Sacramento River water right. The governor's office said the next day that all regulatory approvals needed to start construction were in place.

  3. Next2027

    Construction start

    The Plan of Finance assumes construction begins in 2027, after financing is advanced.

  4. ExpectedJanuary 2027

    Local creeks water-right hearing

    A separate hearing on whether the project may also capture water from Funks and Stone Corral creeks is scheduled to begin in January 2027.

  5. Expected2034

    Substantial completion and first fill

    The Plan of Finance anticipates substantial completion and the start of first fill in 2034, with start-up and punch-list work continuing through 2035.

Worth knowing

Last checked Nov 23, 2026. We add a step when it happens and link the source.