Track your favorite projects · Water
Sites Reservoir, Sacramento Valley
A planned off-stream reservoir of up to 1.5 million acre-feet, now fully permitted for construction once financing is in place.
Show on the map: Sites Reservoir, Sacramento Valley
- InvestmentAbout $8.1 billion in 2026 dollars. The 2024 governance estimate was $7.5 billion; year-of-expenditure cost is about $9.9 billionSites Project Authority, Oct 19, 2026
- CapacityUp to 1.5 million acre-feet, filled from high Sacramento River flowsOffice of the Governor of California, Nov 5, 2026
- Water rightThe State Water Board approved a Sacramento River water right on Nov 4, 2026, allowing diversions of up to 986,000 acre-feet a year, only in high-flow periods from November to mid-JuneCalifornia State Water Resources Control Board, Nov 4, 2026
- State fundingAbout $1.36 billion in eligible state funding, after nearly $269 million added in June 2026Office of the Governor of California, Nov 5, 2026
Next gate
Construction start
Assumed in 2027, after financing
The governor's office said all regulatory approvals needed to start construction are in place and that the authority is now advancing financing. The Plan of Finance assumes construction begins in 2027.
Every step so far, and what comes next
-
DoneOctober 2026
Plan of Finance published
The authority published a plan based on August 2026 assumptions, including an $8.1 billion 2026-dollar estimate and a 2027 to 2035 construction period.
-
DoneNov 4, 2026
Water right approved
The State Water Board approved the project's Sacramento River water right. The governor's office said the next day that all regulatory approvals needed to start construction were in place.
Source: California State Water Resources Control Board, Nov 4, 2026
-
Next2027
Construction start
The Plan of Finance assumes construction begins in 2027, after financing is advanced.
-
ExpectedJanuary 2027
Local creeks water-right hearing
A separate hearing on whether the project may also capture water from Funks and Stone Corral creeks is scheduled to begin in January 2027.
Source: California State Water Resources Control Board, Nov 4, 2026
-
Expected2034
Substantial completion and first fill
The Plan of Finance anticipates substantial completion and the start of first fill in 2034, with start-up and punch-list work continuing through 2035.
Worth knowing
- The map uses $8.1 billion, the estimate in 2026 dollars. The year-of-expenditure figure is about $9.9 billion.
- Construction in 2027 is a planning assumption and still depends on financing.
- The Nov 4 water right covers Sacramento River diversions only. A separate hearing on Funks and Stone Corral creeks is scheduled to begin in January 2027.
- Dates are planning targets, not a fixed construction commitment.
Last checked Nov 23, 2026. We add a step when it happens and link the source.
Tracking saves to this device only. No account, no email, free.